P. Way Related Question Bank for Engineering Department
Exam
Question 1. As a SSE / JE (P way) (not- in-charge), foot
inspection of his entire jurisdiction should be carried out once in ________
months.
Option
a) 1
b) 6
c) 12
Answer - b) 6
Question 2. As a SSE / JE (P Way) ( in-charge), push
trolley inspection of his entire jurisdiction with PSC sleeper should be
carried out once in ________ months.
Option
a) 1
b) 6
c) 12
Answer - a) 1
Question 3. Curve is inspected once in ___ months in A
route with PSC sleeper by JE/SE/ P. Way in rotation.
Option
(a) 4
b) 2
c) 6
Answer - c) 6
Question 4. Schedule of inspection of monsoon patrolling
by train is once in ________ for JE/II/ P. Way.
Option
a) fortnight
b) a month
c) a week
Answer - a)
fortnight
Question 5. ERC in _______ number of PSC sleepers have to
be greased during key man’s daily inspection when his entire length is with PSC
sleeper
Option
a) 80
b) 20
c) 10
Answer - b) 20
Question 6. Tools and equipment with gang has to be
inspected once in _____ by JE /P. way
Option
a) fortnight
b) a month
c) a week
Answer - b) a
month
Question 7. Points and crossing on non running line has to
be inspected once in ________ months by JE/SE on rotation
Option
a) 6
b) 3
c) 1
Answer - a) 6
Question 8. The SSE / JE (Pway) (in-charge), has to
inspect the small track machines once in ______ .
Option
(a) a fort night
b) a month
c) 3 months
Answer - (a) a
fort night
Question 9. Gang mate has to perform the key man
patrolling once a ______.
Option
(a) fortnight
b) week
c) month
Answer - b)
week
Question 10. If
prima facie cause of accident is rail fracture, the fractured rail pieces are
sent to ______
Option
Question a) CMT/PER
b) RDSO
c) Rly Board
Answer - b)
RDSO
Question 11. Chamfering
of rail holes reduces stress concentration by ________ %
Option
a) 14
b) 24
c) 4
Answer - a) 14
Question 12. In need-based
system of USFD testing of rails, the interval between successive tests in the
field will be after the passage of ____ subject to a maximum interval of 24
months.
Option
(a) 5
b) 8
c)12
Answer - b) 8
Question 13. If
flame cutting of rail is unavoidable, preheating of ____ mm on either side has
to be done before cutting
Option
a) 500
b) 100
c) 300
Answer - b) 100
Question 14. Second
coat in the anticorrosive treatment of rails will be given with _____ emulsion.
Option
(a) black
b) bituminous
c) IS - 158
Answer - b)
bituminous
Question 15. Combination
joints are provided with __________ mm gap
Option
a) 6
b) 10
c) 0
Answer - c) 0
Question 16. ________
is used for using wornout fish plates in the track
Option
a) shim
b) saddle plate
c) half moon washer
Answer - a) shim
Question 17. Rail
with rolling mark 60 880 SAIL 0 XI / 2002 indicates _________ grade rail
Option
a) 60
b) 880
c) 0
Answer - b) 880
Question 18. Rail of 13 m length should be transported by
____numbers of dip lorries.
Option
(a) 1
(b) 2
(c) 13
Answer - (b) 2
Question 19. Maximum
permissible vertical wear for 60kg rail section ___ mm
Option
(a) 12
(b)15
(c)13
Answer - (c)13
Question 20. ‘E’ route BG Track with annual GMT of more
than 20 should have minimum rail section of _____ kg
Option
a) 52 kg 880 grade
b) 60 kg
c) 52 kg 710 grade
Answer - b) 60
kg
Question 21. ____
route in NE Railway is classified as 'D spl' route
Option
a. GKC-BBK
b) BTT-ARJ
c) RMU-KGM
Answer - a. GKC-BBK
Question 22. IMR
defective rails shall be replaced with in _______ days.
Option
(a) 1
b. 3
c. 15
Answer - b. 3
Question 23. DFW welds secured with joggled fish plates and
clamps shall be replaced with in _____ days.
Option
(a) 3
b. 15
c. 3
months
Answer - b. 15
Question 24. The
frequency of SKV weld testing in sections having 40 GMT is once in ______ years.
Option
(a) 2
b. 3
c. 4
Answer - b. 3
Question 25. The
frequency of rail testing in sections having 48 GMT is once in _______ months.
Option
(a) 1. 5
b. 2
c. 3
Answer - b. 2
Question 26. The
double rail tester of USFD machine is having ________ No. of
probes.
Option
(a) 4
b. 5
c. 10
Answer - c. 10
Question 27. Grooved
rubber pad used on 60 kg PSC sleeper is T-___.
Option
(a) 3706
b) 3703
c) 3711
Answer - c)
3711
Question 28. T
3707 GFN liners are used at __________ side when 52 kg rail is fixed on T2496
PSC sleepers in track circuited area
Option
a) gauge
b) non gauge
c) not applicable
Answer - a) gauge
Question 29. In
toe load testing of ERC if 20% of sample size or more records less than 600kg
of toe load, then double the _____________ .
Option
(a) frequency of inspection
b) sample size
c) both a & b
Answer - c)
both a & b
Question 30. Sleeper
density of 1660 nos/km has a sleeper spacing of _________ cm
Option
a) 55
b) 60
c) 65
Answer - b) 60
Question 31. PSC
sleeper is having ______ scrap value
Option
a. 0
b) less
c) more
Answer - a. 0
Question 32. _______mm
is the nominal gauge for new BG PSC sleepers
Option
a) 1673
b) 1676
c) 1679
Answer - a) 1673
Question 33. GFN
liner used for fixing 52 kg rail on T2495 PSC sleeper is _____
Option
a) T3702
b) T3706 (GF)
c) T3707 (GF) & T3708
(NGF)
Answer - a) T3702
Question 34. Greasing
of ERC is carried out once in ___________ months for normal area.
Option
(a) 6
b) 12
c) 24
Answer - c) 24
Question 35. Sleeper
spacing on curved track marked on ____ rail
Option
(a) inner
(b) outer
(c) either inner or outer
Answer - (b)
outer
Question 36. Mass
lubrication of ERCs is carried out by keeping ____ sleepers on either side
intact
Option
(a) 15
(b) 10
(c) 30
Answer - (a) 15
Question 37. Minimum
ballast cushion for 22. 1T axle load
route is _________mm.
Option
a) 250
b) 300
c) 350
Answer - c) 350
Question 38. Measured
ballast stack are identified by ______
a) Sprinkling cement mortar
b) sprinkling lime
c)sprinkling sand
Answer - b)
sprinkling lime
Question 39. Ballast
deficiency is assessed for deep screening work at 2-3 sleeper bay for
every_______
Option
a) km
b) Hectometre
c) 2 km
Answer - a) km
Question 40. ____
number of stacks can be collected in a Plot of a ballast depot
Option
a) 4
b) 2
c) 1
Answer - c) 1
Question 41. Unloading
of ballast at centre of track and at shoulder is done by using ________ wagons.
Option
(a) BKH
b) BOB
c) BOX
d) BOBYN
Answer - d)
BOBYN
Question 42. Retention
of ballast in sieve analysis is determined by _________
Option
a) Weight
b) Volume
c) both a & b
Answer - a) Weight
Question 43. Abrasion
and impact value for ballast are tested for supply of ballast for every ______
cum
Option
a) 1000
b) 2000
c) 5000
Answer - b)
2000
Question 44. The
bridge is classified as _________ Bridge when total linear water way is 350m
Option
a. minor
b. major
c. important
Answer - c. important
Question 45. Trolley
refuges are provided for bridges having main spans less than 100m at every
__________m
Option
a) 200
b) 100
c) 50
Answer - b) 100
Question 46. ____
bearing plates can be used over girder bridges
Option
a) canted
b) Anti creep
c) special size
Answer - a) canted
Question 47. Converging
of guard rails for BG track over girder bridge is laid for a length of _____ mm.
Option
(a) 3660
b) 4875
c) 1800
Answer - b)
4875
Question 48. Clear
spacing of bridge timber on BG new track should not be more than ______mm
Option
a) 450
b) 510
c) 200
Answer - a) 450
Question 49. ____
mm is the distance between guard rail and running rail of MG track over bridges
.
Option
(a) 250
b) 200
c) 150
Answer - b)
200
Question 50. Hook
bolts used for plate girder bridges are___ type
Option
a) Sloping leg
b) straight leg
c) any of the above
Answer - b)
straight leg
Question 51. Clear
spacing of bridge timber at rail joints on BG track should not be more than
__________ mm
Option
(a) 500
(b)450
(c) 200
Answer - (c)
200
Question 52. The
length of a BG bridge sleeper is outside to outside of girder flanges plus
305mm but not less than ______mm
Option
a) 2440
b) 2750
c) 3050
Answer - a) 2440
Question 53. Minimum
thickness of BG bridge sleeper excluding notching is _________ mm.
Option
(a) 150
(b)175
(c)200
Answer - (a) 150
Question 54. As
an alternative to wooden sleeper, __________ sleepers are used in railway steel
girder bridges.
Option
(a) steel trough
(b) steel channel
(c) CST-9
Answer - (b)
steel channel
Question 55. The
size of auger used for fixing rail in Bridge timber is _______ mm
Option
a) 18
b) 20
c) 22
Answer - b) 20
Question 56. The
PSC sleeper to RDSO Drg. no. T-
4088-4097 are used at the _______ of bridges.
Option
(a) center
b. end
c. approaches
Answer - c. approaches
Question 57. The danger mark is painted in ____ colour in
bridges
Option
a) yellow
b) red
c) white
Answer - b) red
Question 58. TBTR
is done in ___________ bridges
Option
a) ballasted
b) girder
c) both a & b
Answer - b)
girder
Question 59. Ballast
penetration profiles should be obtained
at ____________ intervals.
Option
(a) every TP
b) every km
c) every hectometre
Answer - (a) every
TP
Question 60. As
per five step method increasing the ballast cushion even up to _________ mm by
raising the track.
Option
(a) 250
b) 350
c) 450
Answer - b) 350
Question 61. The
minimum thickness of blanket is ___________ mm in ordinary clay soil.
Option
a) 300
b) 500
c) 1000
Answer - a) 300
Question 62. The
recommended formation width for BG double line embankment is __________ mm.
Option
a) 11550
b) 12150
c) 6850
Answer - b)
12150
Question 63. The
catch water drain should be provided _________ meter away from the edge of
cutting.
Option
(a) 2
b) 3
c) 5
Answer - (a) 2
Question 64. The
bank side slope should be __________ for good formation soil.
Option
(a) 2:1
b) 1:2
c) 1:1
Answer - (a) 2:1
Question 65. The
slope of top of formation should be ______.
Option
a) 1 in 20
b) 1 in 60
c) 1 in 40
Answer - c) 1
in 40
Question 66. Soil
should be filled in layers of __________ cm thickness before consolidation.
Option
a) 15
b) 30
c) 45
Answer - b) 30
Question 67. Service
tolerance of gauge is ________ mm for 500m radius curved BG track
Option
a) -6 to +6
b) -6 to +15
c) Up to + 20
Answer - b) -6
to +15
Question 68. A ramp of 1 in ____ has to be ensured during
major lifting of track before allowing the train over the work spot
Option
a) 100
b) 200
c) 500
Answer - c) 500
Question 69. Distance
pieces to platform lines are provided for every __________m
Option
a) 30
b) 100
c) 50
Answer - a) 30
Question 70. Max.
Permissible creep in IR is ____________
Option
a) 50
b) 150
c) 250
Answer - b) 150
Question 71. The
Gauge is measured ___ mm below rail top in the track
Option
a) 13
b) 0
c) 19
Answer - a) 13
Question 72. Grease
and k. oil are mixed in ________
proportion to form stiff paste for lubricating fishplate
Option
a) 3 :2
b) 4:7
c) 1:1
Answer - a) 3
:2
Question 73. _______
m length of track can be left unscreened in a day’s (deep, screening) work
Option
(a) 13
b) 100
c) 0
Answer - c) 0
Question 74. Shallow
screening of crib ballast is carried out up to ____mm below bottom of sleeper
in machine maintained section
Option
a) 50-75
b) 25 - 50
c) 75-100
Answer - c)
75-100
Question 75. The
screen is inclined at an angle not less than ______ ˚ to vertical in deep
screening work.
Option
a) 30
b) 45
c) 60
Answer - c) 60
Question 76. Serial
number of sleepers begin at every _______.
a) p. way
section
b) km
c) gang length
Answer - b) km
Option
Question 77. Sighting
of rail for lifting track is done by viewing ____
Option
a) Top of rail table on gauge
face side
b) top of rail table on non
gauge face side
c) bottom of rail table on non
gauge face side
Answer - c)
bottom of rail table on non gauge face side
Question 78. Rails
are identified as LH / RH along the ________ in case of single line section
Option
a) traffic
b) increasing km
c) both a & b
Answer - b)
increasing km
Question 79. ______
joints are not lubricated.
Option
a) insulated
b) combination
c) both a & b
Answer - a) insulated
Question 80. Each gang chart is meant for ___________
months
Option
a) 3
b) 6
c) 12
Answer - b) 6
Question 81. Pre
tamping works are to be done by ___ in 3 tier system of maintenance
Option
a) OMU
b) MMU
c) sectional gangs
Answer - c)
sectional gangs
Question 82. ____
activity is not carried by TTM during tamping work
Option
a) packing
b) aligning
c) boxing
Answer - c)
boxing
Question 83. ____________are
used to find out crack in bottom of rail
Option
a) Mirror
b) Magnifying glass
c) Both a & b
Answer - c)
Both a & b
Question 84. In
Deep screening process, the screen of size _____ mm is used for manual deep
screening.
Option
a) 50 x 50
b) 30 x 30
c) 45 x 45
Answer - b) 30
x 30
Question 85. ___
ballast is not screened in shallow screening
Option
a) crib
b) shoulder
c) cushion
Answer - c)
cushion
Question 86. Deep
screening of plain track is carried out once in ____ years
Option
a) 10
b) 3
c) 2
Answer - a) 10
Question 87. The curve shall be realigned within _____ from
the date of measurement.
Option
a) a week
b) fortnight
c) a month
Answer - c) a
month
Question 88. The curve is measured with versine to an
accuracy of ____mm
Option
a) 2
b) 1
c) 5
Answer - b) 1
Question 89. The curve in BG A route track shall be
measured on ____ m chord.
Option
a) 10
b) 20
c) 6
Answer - b) 20
Question 90. Minimum radius of a turn in curve in BG is
___m
Option
a) 165
b) 220
c) 350
Answer - c) 350
Question 91. Cant gradient of 0. 25% induces inbuilt twist of _________ mm/m
Option
a) 0. 25
b) 2. 5
c) 5
Answer - b) 2. 5
Question 92. Super elevation difference between two
consecutive stations on a BG curved track should not exceed ________ mm without
CE’s approval.
Option
a) 14
b) 28
c) 35
Answer - a) 14
Question 93. __________ type junction of gradients leads to
bunching of vehicles.
Option
(a) sag
b) summit
c) both a & b
Answer - (a) sag
Question 94. Minimum radius of a vertical curve on Gr. D route
is _________ m.
Option
a) 2500
b) 3000
c) 4000
Answer - a) 2500
Question 95. New track laid over a BG curve of 6 degree
shall have gauge up to ______mm
Option
a) +10
b) +15
c) +20
Answer - a) +10
Question 96. On curves, _______ rail is taken as reference
for longitudinal level.
Option
a) outer
b) any
c) inner
Answer - c)
inner
Question 97. Reverse curve on BG high speed route should
have a minimum straight of ______m between curves.
Option
a) 30
b) 50
c) 10
Answer - b) 50
Question 98. Speed of goods train on T/O on 1 in 8 ½ of
straight switch layout is ____kmph
Option
a) 10
(b) 15
(c) 30
Answer - a) 10
Question 99. Maximum degree of BG curve is _______.
Option
(a) 15
(b) 10
(c) 5
Answer - b) 10
Question 100. ___________ is provided on curve to balance
the centrifugal force.
Option
(a) cant
b) shift
c) cant excess
Answer - (a) cant
Question 101. If a 1 in 12 turn out with curved switch takes
off from the outside of BG curve of 350 m radius, the type of turn out will be
________ .
Option
(a) similar flexure
b) contra flexure
c) symmetrical split
Answer - (a) similar
flexure
Question 102. 1 in 8. 5 Turn outs should not normally take off from
________ curve.
Option
(a) inside
b) outside
c) any side
Answer - (a) inside
Question 103. Equilibrium cant for minimum sectional speed +
________ = Actual cant.
Option
(a) cant deficiency
(b) cant excess
(c) rate of change of cant
Answer - (b) cant
excess
Question 104. In IR, transition curve shape is _________
Option
(a) cubical parabola
(b) spiral
(c) clothoidal
Answer - (a) cubical
parabola
Question 105. Mid stagger joints are provided on BG 13 m
rail curved track of radius ___.
Option
(a) less than 400m
(b)more than 400m
(c)more than 600m
Answer - (a) less
than 400m
Question 106. Maximum permissible cant on BG Group D route
is ______ mm
Option
a) 165
b) 140
c) 100
Answer - b) 140
Question 107. If versine of 100 mm is measured over 20 m
chord on the circular curve, radius of the curve is designated as ________ m.
Option
(a) 500
(b)1000
(c) 1500
Answer - (a) 500
Question 108. Versine in cm measured on ___ m chord of curve
gives te degree of curve.
Option
a) 20
b) 6
c) 11. 8
Answer - c) 11.
8
Question 109. Virtual transition length on BG is _______m
Option
a) 14. 6
b) 13. 7
c) 20
Answer - a) 14.
6
Question 110. _______ mm/sec is the maximum rate of change
of cant permissible on BG routes.
Option
(a) 35
b) 55
c) 25
Answer - b) 55
Question 111. ____ Authority will be given by the gateman
after closing and locking the Level Crossing gate against road traffic
Option
a) Private Number
b) LB
c) look out caution
Answer - a) Private
Number
Question 112. In an unmanned Level Crossing, ______ board
for road users should be provided in the road approaches at 5m from the centre
of nearest track.
Option
a) Stop
b) caution
c) speed
Answer - a) Stop
Question 113. Census at Level Crossing shall be taken by
____ department only.
Option
(a) engineering
b. personnel
c. none
Answer - c. none
Question 114. In case of an obstruction at Level Crossing,
banner flag should be displayed at a distance of 5 m from ___________.
Option
(a) end of Level Crossing
(b) end of check rail
(c) end of gate lodge
Answer - (b)
end of check rail
Question 115. Cleaning of flange way of check rails is done
by ___ in UM Level Crossing
Option
a) gang mate
b) GK
c) key man
Answer - c) key
man
Question 116. Level Crossing having TVU > 50000 is
classified as ____ category
Option
a) B1
b) A
c) Special
Answer - c)
Special
Question 117. ____ gradient shall be provided on road
surface within gates in Level Crossing
Option
a) No
b) 1 in 30
c) 1 in 40
Answer - a) No
Question 118. The census is taken once in ___ years
Option
a) 1
b) 3
c) 5
Answer - b) 3
Question 119. Height gauge is provided at a distance of ___m
from the gate in Level Crossing
Option
a) 3
b) 5
c) 8
Answer - c) 8
Question 120. Hot weather patrolling is introduced when the
prevailing rail temperature falls above Td ____ 0 C.
Option
(a) +10
b) -20
c) +20
Answer - c) +20
Question 121. Manual packing in LWR track should be done,
when the prevailing rail temperature is between ____0 C
Option
(a) td + 20 and td – 30
(b) td + 10 and td – 30
(c) td + 20 and td – 20
Answer - (b) td
+ 10 and td – 30
Question 122. Glued joints used in LWR should be
_________ type
Option
a) G3S
b) G3L
c) both a & b
Answer - b) G3L
Question 123. The gradient shall not be steeper than 1 in
___ for laying LWR
Option
a) 50
b) 100
c) 25
Answer - b) 100
Question 124. The other thermometer is checked for
accuracy with ___ type thermometer
Option
a) dial
b) embedded
c) pen
Answer - b)
embedded
Question 125. Temporary destressing is not required for deep
screening when prevailing rail temperature is < Td +____ 0 C
Option
a) +10
b) +20
c) +30
Answer - a) +10
Question 126. Rollers shall be placed at every __ sleepers
during destressing
Option
a) 25
b) 15
c) 50
Answer - b) 15
Question 127. The shoulder ballast shall be heaped over ___
mm above top of sleeper for LWR track
Option
a) 50
b) 100
c) 150
Answer - b) 100
Question 128. Minimum level of supervision of renewing
fastenings in LWR track with lifting is ___
Option
a) key man
b) gang mate
c) JE
Answer - b)
gang mate
Question 129. _________ Patrolling is introduced during
civil disturbance.
Option
a) monsoon
b) emergency
c) security
Answer - c)
security
Question 130. Emergency patrol can be introduced by _______
of gang.
Option
a) key man
b) gang mate
c) track man
Answer - b)
gang mate
Question 131. Beat length of each patrol man should not
exceed _________ km.
Option
a) 5
b) 10
c) 15
Answer - a) 5
Question 132. The maximum walking speed of monsoon patrol
man is _________ kmph
Option
a) 5
b) 8
c) 3
Answer - c) 3
Question 133. Tapered washers are used in ___________
Option
a) built up crossing
b) CMS crossing
c) obtuse crossing
Answer - b) CMS
crossing
Question 134. ______ mm is deducted from measured wear of 52
kg CMS Xing to get actual wear of Xing.
Option
a) 2
b) 2. 5
c) 0
Answer - a) 2
Question 135. Before reconditioning, ______crossing is
preheated.
Option
a) built up
b) CMS
c) obtuse
Answer - a) built
up
Question 136. Turn out curvature starts from actual toe of
switch for _______switches
Option
a) straight
b) curved
c) both a & b
Answer - b)
curved
Question 137. ___________ heel type of switch is most
preferable.
Option
a) loose
b) fixed
c) two fit
Answer - b)
fixed
Question 138. The sleeper spacing of 1 in 12 fan shaped
layout is marked on ____ rails only
Option
a) main line
b) turn out rails
c) lead rails
Answer - a) main
line
Question 139. _____type of electrodes are used for
reconditioning of curved switches
Option
a) H3
b) H3A
c) both a & b
Answer - c)
both a & b
Question 140. The end bend of wing rail is called as
___________
Option
a) flare
b) toe
c) heel
Answer - a) flare
Question 141. LH tongue rail of RH curved switch BG turnout
shall be ________
Option
a) curved
b) straight
c) partly curved
Answer - a) curved
Question 142. Interlocked points are attended in presence of
_______________ staff.
Option
(a) TRD
b) mechanical
c) signal
Answer - c)
signal
Question 143. Turn in curve is measured on ____ m chords at
___ m interval.
Option
(a) 6 & 3
b) 3 & 6
c) 20 & 10
Answer - (a) 6
& 3
Question 144. The gauge at 150 mm behind nose of CMS Xing in
fan shaped layout is ____ .
Option
(a) 1676
b) 1673
c) 1679
Answer - b)
1673
Question 145. The gap between lead rail and toe of CMS
crossing is ___ mm.
Option
a) 6
b) 4
c) 0
Answer - c) 0
Question 146. Obtuse crossing check rail is raised by____ mm
over rail top table
Option
a) 13
(b) 39
(c) 25
Answer - (c) 25
Question 147. Heel divergence is ______ mm for BG 1 in 8 ½
curved switch turnout.
Option
(a) 136
b) 175
c) 182. 5
Answer - c) 182.
5
Question 148. Tongue rail table is ______ mm higher than
stock rail table at heel of switch for thick web switch
Option
a) 6
b) 0
c) 12
Answer - b) 0
Question 149. The gauge in ATS is ________ mm for 1 in 12
PSC fan shaped layout
Option
a) 1673
b) 1676
c) 1679
Answer - a) 1673
Question 150. Stretcher bar is assembled by keeping ____the
throw of switch
Option
a) full
b) half
c) quarter
Answer - b)
half
Question 151. The limiting vertical wear of 60 kg tongue
rail is ______ mm of 1 in 12 fan shaped layout.
Option
(a) 8
b) 13
c) 10
Answer - (a) 8
Question 152. The minimum gap between top of leading
stretcher bar and bottom of stock rail of a new point shall be ___mm
Option
a) 5
(b) 1. 5
c) 0
Answer - (b) 1.
5
Question 153. Lubrication of rail joints comes under work of
___________
Option
(a) short duration
(b) long duration
(c) line block
Answer - (a) short duration
Question 154. Rail renewal is carried out with ________
protection
Option
(a) short duration
(b) long duration
(c) line block
Answer - (c)
line block
Question 155. RAW means _______
Option
a) Rain affecting works
b) Railway affecting water
c) Railway affecting works
Answer - c)
Railway affecting works
Question 156. The accident due to failure of ______ is
classified under K category.
Option
a) P. Way
b) signal
c) mechanical
Answer - a) P. Way
Question 157. Speed indicator is provided at __m from work
spot when one speed restriction is in force
Option
a) 600
b) 5
c) 30
Answer - c) 30
Question 158. Stop indicator will be provided in the Level
Crossing road approaches at 5m from the ___
Option
a) gate
b) centre of nearest track
c) centre of road
Answer - b)
centre of nearest track
Question 159. Deep screening comes under work of ___________
Option
(a) short duration
(b) long duration
(c) line block
Answer - (b)
long duration
Question 160. Speed indicator will be erected at a height of
_______ m from rail level
Option
a) 1. 65
b) 2. 5
c) 2
Answer - c) 2
Question 161. Termination indicator will be erected at a
height of _______ m from rail level
Option
(a) 2. 25
(b) 1. 65
(c) 2. 0
Answer - (b) 1.
65
Question 162. Caution indicator is provided at a distance of
___m from BG work spot.
Option
a) 600
b) 30
c) 1200
Answer - c)
1200
Question 163. Minimum level of supervision for rail dolley
working is _____
Option
a) JE
b) Gang mate
c) key man
Answer - c) key
man
Question 164. Detonators can be used in main line for ___
years.
Option
a) 8
b) 17
c) 3
Answer - a) 8
Question 165. The caution indicator is provided at ___ m
height above rail level.
Option
(a) 1
b) 1. 5
c) 2
Answer - c) 2
Question 166. Engineering indicators are used for work of
_____ duration.
Option
(a) long
b) short
c) both a & b
Answer - (a) long
Question 167. Minimum check rail clearance of 52 kg CMS Xing
used for PSC layout is _____ mm.
Option
a) 41
b) 44
c) 51
Answer - a) 41
Question 168. The minimum Check rail clearance at Level
Crossing is ____ mm
Option
(a) 47
(b) 51
(c) 67 m
Answer - (b) 51
Question 169. The Permissible throw of switch in new BG
turnout is _____ mm.
Option
a) 115
b) 100
c) 95
Answer - a) 115
Question 170. Min. height of FOB at the centre of a BG track in
electrified sections is ________mm.
Option
a. 5870
b. 6100
c. 6250
Answer - c. 6250
Question 171. Min. height of a BG high level passenger platform
from rail level is _____mm
Option
a) 760
b) 840
c) 1035
Answer - a) 760
Question 172. SWR can be continued over bridge upto a span
of _______ m for unsymmetrical condition.
Option
(a) 13. 3
b) 6. 1
c) 30. 5
Answer - b) 6. 1
Question 173. SWR shall not be laid over curved PSC sleeper
track with Radius less than _____ metre
Option
a) 500
b) 440
c) 875
Answer - b) 440
Question 174. Gap Survey is conducted once in ______
Option
a) a month
b) a year
c) fortnight
Answer - b) a
year
Question 175. The fish plated joints of SWR track at level
crossing shall not be located with in ____ m from end of Level Crossing.
Option
(a) 3
b) 0
c) 6
Answer - c) 6
Question 176. Gap survey shall be carried out when the rail
temperature is in _____ trend only.
Option
(a) rising
b) falling
c) both a & b
Answer - (a) rising
Question 177. Profiling and distribution of ballast is
carried out by ________ machine
Option
a) BRM
b) BCM
c) PQRS
Answer - a) BRM
Question 178. ___ number of insertions is given per sleeper
by TTM when BG PSC sleeper track is lifted by 50 mm.
Option
a) 1
b) 2
c) 3
Answer - b) 2
Question 179. Motorized trolleys in T-28 machine shall shift
the loaded P&C to a maximum of ______ mm to avoid infringements
Option
a) 450
b) 300
c) 750
Answer - b) 300
Question 180. In smoothening mode of TTM working with four-point
lining method, the residual error ratio is 1: ____.
Option
(a) 3. 14
b) 6. 09
c) 1
Answer - b) 6. 09
Question 181. The machine that pack 3 sleepers at a time is
_____
Option
a) Unimat
b) CSM
c) Tamping Express
Answer - c)
Tamping Express
Question 182. Generally, in BCM working, the machine can
screen the ballast for a width of ____ mm
Option
a) 3400
b) 2750
c) 4100
Answer - c)
4100
Question 183. The tamping cycle for track having other than
PSC sleeper is once in ______ years.
Option
(a) 1
b) 2
c) 3
Answer - b) 2
Question 184. The dynamic gauge of auxiliary track is ___ mm
in PQRS work.
Option
a) 1750
b) 1673
c) 3400
Answer - c)
3400
Question 185. Alignment correction can be made when UNIMAT
work on _____ track only.
Option
a) main line
b) turnout
c) any
Answer - a) main
line
Question 186. Design mode of working of Tamping machines
cause _________ residual error.
Option
(a) 1: 3. 14
b) 1: 6. 09
c) zero
Answer - a) main
line
Question 187. ___ based method suitable for isolated
attention in track monitoring
Option
a) peak
b) SD
c) both a & b
Answer - a) peak
Question 188. The BG track with section speed more than 110
kmph having > ___g location require attention
Option
a) 0. 15
b) 0. 2
c) 0. 1
Answer - a) 0. 15
Question 189. OMS inspection for track with 100 kmph is once
in ___ months
Option
a) 1
b) 2
c) 4
Answer - b) 2
Question 190. Minimum height of a 52 kg rail section for AT
welding of rail joints is ____mm
Option
a) 156
b) 150
c) 153
Answer - b) 150
Question 191. _____ fuel is adopted for AT welding of rail
joints.
Option
(a) Air - petrol
(b) LPG-OXY
(C) both a & b
Answer - (C)
both a & b
Question 192. If 880 grade rail has to be welded with 710
grade rail in unavoidable circumstances, welding portion to be used should be
________ grade.
Option
a) 1000
b) 710
c) 880
Answer - c) 880
Question 193. During AT welding of rail joints using second
hand rails , old AT weld and ____ mm length on either side should be removed.
Option
(a) 85
(b) 100
(c) 150
Answer - (c) 150
Question 194. Gap for SKV type of AT weld is ___ mm
Option
(a) 20± 1
(b) 25± 1
(c) 30 ± 1
Answer - (b)
25± 1
Question 195. Fastenings of at least ___ sleepers on either
side should be made free before welding in the track.
Option
(a) 2
(b) 4
(c) 5
Answer - (c) 5
Question 196. At least _____ no. of
supports should be provided on either side for cess welding
Option
(a) 5
(b) 2
(c) 10
Answer - (c) 10
Question 197. The tolerance for the finished welds of
lateral alignment is ______ mm on 10 cm straight edge.
Option
a) +/- 1
b) +/- 0. 5
c) +/- 0. 3
Answer - c) +/-
0. 3
Question 198. The railway boundary stones are provided at
every ___.
Option
a) 50m
b) change in alignment
c) both a & b
Answer - c)
both a & b
Question 199. The Stock indent is prepared in _________
number of copies.
Option
a) 2
b) 6
c) 5
Answer - b) 6
Question 200. The accounts stock verification of P. WAY materials are conducted once in ______
years
Option
a) 1
b) 2
c) 3
Answer - a) 1