Question 1.   As a SSE / JE (P way) (not- in-charge), foot inspection of his entire jurisdiction should be carried out once in ________ months.   

Option

a) 1

b) 6

c) 12

Answer - b) 6

 

Question 2.   As a SSE / JE (P Way) ( in-charge), push trolley inspection of his entire jurisdiction with PSC sleeper should be carried out once in ________ months.   

Option

 

a) 1

b) 6

c) 12

Answer - a) 1

Question 3.   Curve is inspected once in ___ months in A route with PSC sleeper by JE/SE/ P.   Way in rotation.   

Option

 

(a) 4

b) 2

c) 6

Answer - c) 6

Question 4.   Schedule of inspection of monsoon patrolling by train is once in ________ for JE/II/ P.   Way.   

Option

 

a) fortnight

b) a month

c) a week

Answer - a) fortnight

 

Question 5.   ERC in _______ number of PSC sleepers have to be greased during key man’s daily inspection when his entire length is with PSC sleeper

Option

a) 80

b) 20

c) 10

Answer - b) 20

 

Question 6.   Tools and equipment with gang has to be inspected once in _____ by JE /P.   way

Option

a) fortnight

b) a month

c) a week

Answer - b) a month

 

 

Question 7.   Points and crossing on non running line has to be inspected once in ________ months by JE/SE on rotation

Option

 

a) 6

b) 3

c) 1

Answer - a) 6

 

 

Question 8.   The SSE / JE (Pway) (in-charge), has to inspect the small track machines once in ______ .   

Option

 

(a) a fort night

b) a month

c) 3 months

Answer - (a) a fort night

 

 

 

Question 9.   Gang mate has to perform the key man patrolling once a ______.   

Option

(a) fortnight

b) week

c) month

Answer - b) week

 

 

 

Question 10.  If prima facie cause of accident is rail fracture, the fractured rail pieces are sent to ______

Option

 

 

Question a) CMT/PER

b) RDSO

c) Rly Board

Answer - b) RDSO

 

 

 

Question 11.  Chamfering of rail holes reduces stress concentration by ________ %

Option

 

a) 14

b) 24

c) 4

Answer - a) 14

 

Question 12.  In need-based system of USFD testing of rails, the interval between successive tests in the field will be after the passage of ____ subject to a maximum interval of 24 months.   

Option

 

(a) 5

b) 8

c)12

Answer - b) 8

 

Question 13.  If flame cutting of rail is unavoidable, preheating of ____ mm on either side has to be done before cutting

Option

 

a) 500

b) 100

c) 300

Answer - b) 100

 

 

Question 14.  Second coat in the anticorrosive treatment of rails will be given with _____ emulsion.   

Option

 

(a) black

b) bituminous

c) IS - 158

Answer - b) bituminous

 

 

Question 15.  Combination joints are provided with __________ mm gap

Option

 

a) 6

b) 10

c) 0

Answer - c) 0

 

 

Question 16.  ________ is used for using wornout fish plates in the track

Option

 

a) shim

b) saddle plate

c) half moon washer

Answer - a) shim

 

 

Question 17.  Rail with rolling mark 60 880 SAIL 0 XI / 2002 indicates _________ grade rail

Option

 

a) 60

b) 880

c) 0

Answer - b) 880

 

 

Question 18.   Rail of 13 m length should be transported by ____numbers of dip lorries.   

Option

 

(a)  1

(b) 2

(c) 13

Answer - (b) 2

 

 

Question 19.  Maximum permissible vertical wear for 60kg rail section ___ mm

Option

 

(a) 12

(b)15

(c)13

Answer - (c)13

 

 

Question 20.   ‘E’ route BG Track with annual GMT of more than 20 should have minimum rail section of _____ kg

Option

 

a) 52 kg 880 grade

b) 60 kg

c) 52 kg 710 grade

Answer - b) 60 kg

 

 

Question 21.  ____ route in NE Railway is classified as 'D spl' route

Option

 

a.   GKC-BBK

b) BTT-ARJ

c) RMU-KGM

Answer - a.   GKC-BBK

 

 

Question 22.  IMR defective rails shall be replaced with in _______ days.   

Option

 

(a) 1

b.  3

c.  15

Answer - b.  3

 

 

Question 23.   DFW welds secured with joggled fish plates and clamps shall be replaced with in _____ days.   

Option

 

(a) 3

b.   15

c.   3 months

Answer - b.   15

 

 

Question 24.  The frequency of SKV weld testing in sections having 40 GMT is once in ______ years.   

Option

 

(a) 2

b.   3

c.  4

Answer - b.   3

 

 

Question 25.  The frequency of rail testing in sections having 48 GMT is once in _______ months.   

Option

 

(a) 1.  5

b.  2

c.  3

Answer - b.  2

 

 

Question 26.  The double rail tester of USFD machine is having ________ No.   of probes.   

Option

 

(a) 4

b.   5

c.  10

Answer - c.  10

 

 

Question 27.  Grooved rubber pad used on 60 kg PSC sleeper is T-___.   

Option

 

(a) 3706

b) 3703

c) 3711

Answer - c) 3711

 

 

Question 28.  T 3707 GFN liners are used at __________ side when 52 kg rail is fixed on T2496 PSC sleepers in track circuited area

Option

 

a) gauge

b) non gauge

c) not applicable

Answer - a) gauge

 

 

Question 29.  In toe load testing of ERC if 20% of sample size or more records less than 600kg of toe load, then double the _____________ .   

Option

 

(a) frequency of inspection

b) sample size

c) both a & b

Answer - c) both a & b

 

 

Question 30.  Sleeper density of 1660 nos/km has a sleeper spacing of _________ cm

Option

 

a) 55

b) 60

c) 65

Answer - b) 60

 

 

Question 31.  PSC sleeper is having ______ scrap value

Option

 

a.   0

b) less

c) more

Answer - a.   0

 

 

Question 32.  _______mm is the nominal gauge for new BG PSC sleepers

Option

 

a) 1673

b) 1676

c) 1679

Answer - a) 1673

 

Question 33.  GFN liner used for fixing 52 kg rail on T2495 PSC sleeper is _____

Option

 

a) T3702

b) T3706 (GF)

c) T3707 (GF) & T3708 (NGF)

Answer - a) T3702

 

 

Question 34.  Greasing of ERC is carried out once in ___________ months for normal area.   

Option

 

(a) 6

b) 12

c) 24

Answer - c) 24

 

 

Question 35.  Sleeper spacing on curved track marked on ____ rail

Option

 

(a)  inner

(b) outer

(c) either inner or outer

Answer - (b) outer

 

 

Question 36.  Mass lubrication of ERCs is carried out by keeping ____ sleepers on either side intact

Option

 

(a)  15

(b) 10

(c) 30

Answer - (a)  15

 

 

Question 37.  Minimum ballast cushion for 22.  1T axle load route is _________mm.   

Option

 

a) 250

b) 300

c) 350

Answer - c) 350

 

 

Question 38.  Measured ballast stack are identified by ______

a) Sprinkling cement mortar

b) sprinkling lime

c)sprinkling sand

Answer - b) sprinkling lime

 

 

Question 39.  Ballast deficiency is assessed for deep screening work at 2-3 sleeper bay for every_______

Option

 

a) km

b) Hectometre

c) 2 km

Answer - a) km

 

 

Question 40.  ____ number of stacks can be collected in a Plot of a ballast depot

Option

 

a) 4

b) 2

c) 1

Answer - c) 1

 

 

Question 41.  Unloading of ballast at centre of track and at shoulder is done by using ________ wagons.   

Option

(a) BKH

b) BOB

c) BOX

d) BOBYN

Answer - d) BOBYN

 

 

Question 42.  Retention of ballast in sieve analysis is determined by _________

Option

 

a) Weight

b) Volume

c) both a & b

Answer - a) Weight

 

 

Question 43.  Abrasion and impact value for ballast are tested for supply of ballast for every ______ cum

Option

 

a) 1000

b) 2000

c) 5000

Answer - b) 2000

 

Question 44.  The bridge is classified as _________ Bridge when total linear water way is 350m

Option

 

a.   minor

b.   major

c.   important

Answer - c.   important

 

 

Question 45.  Trolley refuges are provided for bridges having main spans less than 100m at every __________m

Option

 

a) 200

b) 100

c) 50

Answer - b) 100

 

 

Question 46.  ____ bearing plates can be used over girder bridges

Option

 

a) canted

b) Anti creep

c) special size

Answer - a) canted

 

 

Question 47.  Converging of guard rails for BG track over girder bridge is laid for a length of _____ mm.   

Option

 

(a) 3660

b) 4875

c) 1800

Answer - b) 4875

 

 

Question 48.  Clear spacing of bridge timber on BG new track should not be more than ______mm

Option

 

a) 450

b) 510

c) 200

Answer - a) 450

 

 

Question 49.  ____ mm is the distance between guard rail and running rail of MG track over bridges .   

Option

 

(a) 250

b) 200

c) 150

 Answer - b) 200

 

 

Question 50.  Hook bolts used for plate girder bridges are___ type

Option

 

a) Sloping leg

b) straight leg

c) any of the above

Answer - b) straight leg

 

 

Question 51.  Clear spacing of bridge timber at rail joints on BG track should not be more than __________ mm

Option

 

(a) 500

(b)450

(c) 200

Answer - (c) 200

 

Question 52.  The length of a BG bridge sleeper is outside to outside of girder flanges plus 305mm but not less than ______mm

Option

 

a) 2440

b) 2750

c) 3050

Answer - a) 2440

 

Question 53.  Minimum thickness of BG bridge sleeper excluding notching is _________ mm.   

Option

 

(a) 150

(b)175

(c)200

Answer - (a) 150

 

 

Question 54.  As an alternative to wooden sleeper, __________ sleepers are used in railway steel girder bridges.   

Option

 

(a)  steel trough

(b) steel channel

(c) CST-9

Answer - (b) steel channel

 

Question 55.  The size of auger used for fixing rail in Bridge timber is _______ mm

Option

 

a) 18

b) 20

c) 22

Answer - b) 20

 

 

Question 56.  The PSC sleeper to RDSO Drg.  no.   T- 4088-4097 are used at the _______ of bridges.   

Option

 

(a) center

b.   end

c.   approaches

Answer - c.   approaches

 

 

Question 57.   The danger mark is painted in ____ colour in bridges

Option

 

a) yellow

b) red

c) white

Answer - b) red

 

 

Question 58.  TBTR is done in ___________ bridges

Option

 

a) ballasted

b) girder

c) both a & b

Answer - b) girder

 

 

Question 59.  Ballast penetration  profiles should be obtained at ____________ intervals.   

Option

 

(a) every TP

b) every km

c) every hectometre

Answer - (a) every TP

 

 

Question 60.  As per five step method increasing the ballast cushion even up to _________ mm by raising the track.   

Option

 

(a) 250

b) 350

c) 450

Answer - b) 350

 

 

Question 61.  The minimum thickness of blanket is ___________ mm in ordinary clay soil.   

Option

 

a) 300

 b) 500

c) 1000

Answer - a) 300

 

 

Question 62.  The recommended formation width for BG double line embankment is __________ mm.   

Option

 

a) 11550

b) 12150

c) 6850

Answer - b) 12150

 

 

Question 63.  The catch water drain should be provided _________ meter away from the edge of cutting.   

Option

 

(a) 2

b) 3

c) 5

Answer - (a) 2

 

 

Question 64.  The bank side slope should be __________ for good formation soil.   

Option

 

(a) 2:1

b) 1:2

c) 1:1

Answer - (a) 2:1

 

 

Question 65.  The slope of top of formation should be ______.   

Option

 

a) 1 in 20

b) 1 in 60

c) 1 in 40

Answer - c) 1 in 40

 

 

Question 66.  Soil should be filled in layers of __________ cm thickness before consolidation.   

Option

 

a) 15

b) 30

c) 45

Answer - b) 30

 

 

Question 67.  Service tolerance of gauge is ________ mm for 500m radius curved BG track

Option

 

a) -6 to +6

b) -6 to +15

c) Up to + 20

Answer - b) -6 to +15

 

 

Question 68.   A ramp of 1 in ____ has to be ensured during major lifting of track before allowing the train over the work spot

Option

 

a) 100

b) 200

c) 500

Answer - c) 500

 

 

Question 69.  Distance pieces to platform lines are provided for every __________m

Option

 

a) 30

b) 100

c) 50

Answer - a) 30

 

 

Question 70.  Max.   Permissible creep in IR is ____________

Option

 

a) 50

b) 150

c) 250

Answer - b) 150

 

 

Question 71.  The Gauge is measured ___ mm below rail top in the track

Option

 

a) 13

b) 0

c) 19

Answer - a) 13

 

 

Question 72.  Grease and k.  oil are mixed in ________ proportion to form stiff paste for lubricating fishplate

Option

 

a) 3 :2

b) 4:7

c) 1:1

Answer - a) 3 :2

 

 

Question 73.  _______ m length of track can be left unscreened in a day’s (deep, screening) work

Option

 

(a) 13

b) 100

c) 0

Answer - c) 0

 

 

Question 74.  Shallow screening of crib ballast is carried out up to ____mm below bottom of sleeper in machine maintained section

Option

 

a) 50-75

b) 25 - 50

c) 75-100

Answer - c) 75-100

 

 

Question 75.  The screen is inclined at an angle not less than ______ ˚ to vertical in deep screening work.  

Option

 

a) 30

b) 45

c) 60

Answer - c) 60

 

 

Question 76.  Serial number of sleepers begin at every _______.   

a) p.   way section

b) km

c) gang length

Answer - b) km

Option

 

 

Question 77.  Sighting of rail for lifting track is done by viewing ____

Option

 

a) Top of rail table on gauge face side

b) top of rail table on non gauge face side

c) bottom of rail table on non gauge face side

Answer - c) bottom of rail table on non gauge face side

 

 

Question 78.  Rails are identified as LH / RH along the ________ in case of single line section

Option

 

 a) traffic

b) increasing km

c) both a & b

Answer - b) increasing km

 

 

Question 79.  ______ joints are not lubricated.   

Option

 

a) insulated

b) combination

c) both a & b

Answer - a) insulated

 

 

Question 80.   Each gang chart is meant for ___________ months

Option

 

a) 3

b) 6

c) 12

Answer - b) 6

 

 

Question 81.  Pre tamping works are to be done by ___ in 3 tier system of maintenance

Option

 

a) OMU

b) MMU

c) sectional gangs

Answer - c) sectional gangs

 

 

Question 82.  ____ activity is not carried by TTM during tamping work

Option

 

a) packing

b) aligning

c) boxing

Answer - c) boxing

 

 

Question 83.  ____________are used to find out crack in bottom of rail

Option

 

a) Mirror

b) Magnifying glass

c) Both a & b

Answer - c) Both a & b

 

 

Question 84.  In Deep screening process, the screen of size _____ mm is used for manual deep screening.   

Option

 

a) 50 x 50

 b) 30 x 30

c) 45 x 45

Answer - b) 30 x 30

 

 

Question 85.  ___ ballast is not screened in shallow screening

Option

 

a) crib

b) shoulder

c) cushion

Answer - c) cushion

 

 

Question 86.  Deep screening of plain track is carried out once in ____ years

Option

 

a) 10

b) 3

c) 2

Answer - a) 10

 

 

Question 87.   The curve shall be realigned within _____ from the date of measurement.   

Option

 

a) a week

b) fortnight

c) a month

Answer - c) a month

 

 

Question 88.   The curve is measured with versine to an accuracy of ____mm

Option

 

a) 2

b) 1

c) 5

Answer - b) 1

 

 

Question 89.   The curve in BG A route track shall be measured on ____ m chord.   

Option

 

a) 10

b) 20

c) 6

Answer - b) 20

 

 

Question 90.   Minimum radius of a turn in curve in BG is ___m

Option

 

a) 165

b) 220

c) 350

Answer - c) 350

 

 

Question 91.   Cant gradient of 0.  25% induces inbuilt twist of _________ mm/m

Option

 

a) 0.  25

b) 2.  5

c) 5

Answer - b) 2.  5

 

 

Question 92.   Super elevation difference between two consecutive stations on a BG curved track should not exceed ________ mm without CE’s approval.   

Option

 

a) 14

b) 28

c) 35

Answer - a) 14

 

 

 

Question 93.   __________ type junction of gradients leads to bunching of vehicles.   

Option

 

(a) sag

b) summit

c) both a & b

Answer - (a) sag

 

 

Question 94.   Minimum radius of a vertical curve on Gr.   D route is _________ m.   

Option

 

a) 2500

b) 3000

c) 4000

Answer - a) 2500

 

 

Question 95.   New track laid over a BG curve of 6 degree shall have gauge up to ______mm

Option

 

a) +10

b) +15

c) +20

Answer - a) +10

 

 

Question 96.   On curves, _______ rail is taken as reference for longitudinal level.   

Option

 

a) outer

b) any

c) inner

Answer - c) inner

 

 

Question 97.   Reverse curve on BG high speed route should have a minimum straight of ______m between curves.   

Option

 

a) 30

b) 50

c) 10

Answer - b) 50

 

 

Question 98.   Speed of goods train on T/O on 1 in 8 ½ of straight switch layout is ____kmph

Option

 

a) 10

(b) 15

(c) 30

Answer - a) 10

 

 

Question 99.   Maximum degree of BG curve is _______.   

Option

 

(a)  15

(b) 10

(c) 5

Answer - b) 10

 

Question 100.   ___________ is provided on curve to balance the centrifugal force.   

Option

 

(a) cant

b) shift

c) cant excess

Answer - (a) cant

 

 

Question 101.   If a 1 in 12 turn out with curved switch takes off from the outside of BG curve of 350 m radius, the type of turn out will be ________ .   

Option

 

(a) similar flexure

b) contra flexure

c) symmetrical split

Answer - (a) similar flexure

 

 

Question 102.   1 in 8.  5 Turn outs should not normally take off from ________ curve.   

Option

 

(a) inside

b) outside

c) any side

Answer - (a) inside

 

 

Question 103.   Equilibrium cant for minimum sectional speed + ________ = Actual cant.   

Option

 

(a) cant deficiency

(b) cant excess

(c) rate of change of cant

Answer - (b) cant excess

 

 

Question 104.   In IR, transition curve shape is _________

Option

 

(a) cubical parabola

(b) spiral

(c) clothoidal

Answer - (a) cubical parabola

 

 

Question 105.   Mid stagger joints are provided on BG 13 m rail curved track of radius ___.   

Option

 

(a) less than 400m

(b)more than 400m

(c)more than 600m

Answer - (a) less than 400m

 

 

Question 106.   Maximum permissible cant on BG Group D route is ______ mm

Option

 

a) 165

b) 140

c) 100

Answer - b) 140

 

 

Question 107.   If versine of 100 mm is measured over 20 m chord on the circular curve, radius of the curve is designated as ________ m.   

Option

 

(a) 500

(b)1000

(c) 1500

Answer - (a) 500

 

 

Question 108.   Versine in cm measured on ___ m chord of curve gives te degree of curve.   

Option

 

a) 20

b) 6

c) 11.  8

Answer - c) 11.  8

 

 

Question 109.   Virtual transition length on BG is _______m

Option

 

a) 14.  6

b) 13.  7

c) 20

Answer - a) 14.  6

 

 

Question 110.   _______ mm/sec is the maximum rate of change of cant permissible on BG routes.   

Option

 

(a) 35

b) 55

c) 25

Answer - b) 55

 

 

Question 111.   ____ Authority will be given by the gateman after closing and locking the Level Crossing gate against road traffic

Option

 

a) Private Number

b) LB

c) look out caution

Answer - a) Private Number

 

 

Question 112.   In an unmanned Level Crossing, ______ board for road users should be provided in the road approaches at 5m from the centre of nearest track.   

Option

 

a) Stop

b) caution

c) speed

Answer - a) Stop

 

 

Question 113.   Census at Level Crossing shall be taken by ____ department only.   

Option

 

(a) engineering  

b.   personnel

c.   none

Answer - c.   none

 

 

Question 114.   In case of an obstruction at Level Crossing, banner flag should be displayed at a distance of 5 m from ___________.   

Option

 

(a)  end of Level Crossing

(b) end of check rail

(c) end of gate lodge

Answer - (b) end of check rail

 

 

Question 115.   Cleaning of flange way of check rails is done by ___ in UM Level Crossing

Option

 

a) gang mate

b) GK

c) key man

Answer - c) key man

 

 

Question 116.   Level Crossing having TVU > 50000 is classified as ____ category

Option

 

a) B1

b) A

c) Special

Answer - c) Special

 

 

Question 117.   ____ gradient shall be provided on road surface within gates in Level Crossing

Option

 

a) No

b) 1 in 30

c) 1 in 40

Answer - a) No

 

 

Question 118.   The census is taken once in ___ years

Option

 

a) 1

b) 3

c) 5

Answer - b) 3

 

 

Question 119.   Height gauge is provided at a distance of ___m from the gate in Level Crossing

Option

 

a) 3

b) 5

c) 8

Answer - c) 8

 

 

Question 120.   Hot weather patrolling is introduced when the prevailing rail temperature falls above Td ____ 0 C.   

Option

 

(a) +10

b) -20

c) +20

Answer - c) +20

 

 

 

Question 121.   Manual packing in LWR track should be done, when the prevailing rail temperature is between ____0 C

Option

 

(a)  td + 20 and td – 30

(b) td + 10 and td – 30

(c) td + 20 and td – 20

Answer - (b) td + 10 and td – 30

 

 

Question 122. Glued joints used in LWR should be _________ type

Option

 

a) G3S

b) G3L

c) both a & b

Answer - b) G3L

 

 

Question 123.   The gradient shall not be steeper than 1 in ___ for laying LWR

Option

 

a) 50

b) 100

c) 25

Answer - b) 100

 

 

Question 124. The other thermometer is checked for accuracy with ___ type thermometer

Option

 

a) dial

b) embedded

c) pen

Answer - b) embedded

 

 

Question 125.   Temporary destressing is not required for deep screening when prevailing rail temperature is < Td +____ 0 C

Option

 

a) +10

b) +20

c) +30

Answer - a) +10

 

 

Question 126.   Rollers shall be placed at every __ sleepers during destressing

Option

 

a) 25

b) 15

c) 50

Answer - b) 15

 

 

Question 127.   The shoulder ballast shall be heaped over ___ mm above top of sleeper for LWR track

Option

 

a) 50

b) 100

c) 150

Answer - b) 100

 

 

Question 128.   Minimum level of supervision of renewing fastenings in LWR track with lifting is ___

Option

a) key man

b) gang mate

c) JE

Answer - b) gang mate

 

 

 

Question 129.   _________ Patrolling is introduced during civil disturbance.  

Option

 

a) monsoon

b) emergency

c) security

Answer - c) security

 

 

Question 130.   Emergency patrol can be introduced by _______ of gang.   

Option

 

a) key man

b) gang mate

c) track man

Answer - b) gang mate

 

 

Question 131.   Beat length of each patrol man should not exceed _________ km.   

Option

 

a) 5

b) 10

c) 15

Answer - a) 5

 

 

Question 132.   The maximum walking speed of monsoon patrol man is _________ kmph

Option

 

a) 5

b) 8

c) 3

Answer - c) 3

 

 

Question 133.   Tapered washers are used in ___________

Option

 

a) built up crossing

b) CMS crossing

c) obtuse crossing

Answer - b) CMS crossing

 

 

Question 134.   ______ mm is deducted from measured wear of 52 kg CMS Xing to get actual wear of Xing.   

Option

 

a) 2

b) 2.  5

c) 0

Answer - a) 2

 

 

Question 135.   Before reconditioning, ______crossing is preheated.  

Option

 

a) built up

b) CMS

c) obtuse

Answer - a) built up

 

 

Question 136.   Turn out curvature starts from actual toe of switch for _______switches

Option

 

a) straight

b) curved

c) both a & b

Answer - b) curved

 

 

Question 137.   ___________ heel type of switch is most preferable.   

Option

 

a) loose

b) fixed

c) two fit

Answer - b) fixed

 

 

Question 138.   The sleeper spacing of 1 in 12 fan shaped layout is marked on ____ rails only

Option

 

a) main line

b) turn out rails

c) lead rails

Answer - a) main line

 

 

Question 139.   _____type of electrodes are used for reconditioning of curved switches

Option

 

a) H3

b) H3A

c) both a & b

Answer - c) both a & b

 

 

Question 140.   The end bend of wing rail is called as ___________

Option

 

a) flare

b) toe

c) heel

Answer - a) flare

 

 

Question 141.   LH tongue rail of RH curved switch BG turnout shall be ________

Option

 

a) curved

b) straight

c) partly curved

Answer - a) curved

 

 

Question 142.   Interlocked points are attended in presence of _______________ staff.   

Option

 

(a) TRD

b) mechanical

c) signal

Answer - c) signal

 

 

Question 143.   Turn in curve is measured on ____ m chords at ___ m interval.   

Option

 

(a) 6 & 3

b) 3 & 6

c) 20 & 10

Answer - (a) 6 & 3

 

 

Question 144.   The gauge at 150 mm behind nose of CMS Xing in fan shaped layout is ____ .   

Option

 

(a) 1676

b) 1673

c) 1679

Answer - b) 1673

 

 

Question 145.   The gap between lead rail and toe of CMS crossing is ___ mm.   

Option

 

a) 6

b) 4

c) 0

Answer - c) 0

 

 

Question 146.   Obtuse crossing check rail is raised by____ mm over rail top table

Option

 

a) 13

(b) 39

(c) 25

Answer - (c) 25

 

 

Question 147.   Heel divergence is ______ mm for BG 1 in 8 ½ curved switch turnout.   

Option

 

(a) 136

b) 175

c) 182.  5

Answer - c) 182.  5

 

 

Question 148.   Tongue rail table is ______ mm higher than stock rail table at heel of switch for thick web switch

Option

 

a) 6

b) 0

c) 12

Answer - b) 0

 

 

Question 149.   The gauge in ATS is ________ mm for 1 in 12 PSC fan shaped layout

Option

 

a) 1673

b) 1676

c) 1679

Answer - a) 1673

 

 

Question 150.   Stretcher bar is assembled by keeping ____the throw of switch

Option

 

a) full

b) half

c) quarter

Answer - b) half

 

 

Question 151.   The limiting vertical wear of 60 kg tongue rail is ______ mm of 1 in 12 fan shaped layout.   

Option

 

(a) 8

b) 13

c) 10

Answer - (a) 8

 

 

Question 152.   The minimum gap between top of leading stretcher bar and bottom of stock rail of a new point shall be ___mm

Option

 

a) 5

(b) 1.  5

c) 0

Answer - (b) 1.  5

 

 

Question 153.   Lubrication of rail joints comes under work of ___________

Option

 

(a)  short duration

(b) long duration

(c) line block

Answer - (a)  short duration

 

 

Question 154.   Rail renewal is carried out with ________ protection

Option

 

(a)  short duration

(b) long duration

(c) line block

Answer - (c) line block

 

 

Question 155.   RAW means _______

Option

 

a) Rain affecting works

b) Railway affecting water

c) Railway affecting works

Answer - c) Railway affecting works

 

 

Question 156.   The accident due to failure of ______ is classified under K category.   

Option

 

a) P.   Way

b) signal

c) mechanical

Answer - a) P.   Way

 

 

Question 157.   Speed indicator is provided at __m from work spot when one speed restriction is in force

Option

 

a) 600

b) 5

c) 30

Answer - c) 30

 

 

 

 

Question 158.   Stop indicator will be provided in the Level Crossing road approaches at 5m from the ___

Option

 

a) gate

b) centre of nearest track

c) centre of road

Answer - b) centre of nearest track

 

 

Question 159.   Deep screening comes under work of ___________

Option

 

(a)  short duration

(b) long duration

(c) line block

Answer - (b) long duration

 

 

Question 160.   Speed indicator will be erected at a height of _______ m from rail level

Option

 

a) 1.  65

b) 2.  5

c) 2

Answer - c) 2

 

 

Question 161.   Termination indicator will be erected at a height of _______ m from rail level

Option

 

(a)  2.  25

(b) 1.  65

(c) 2.  0

 

Answer - (b) 1.  65

 

 

Question 162.   Caution indicator is provided at a distance of ___m from BG work spot.   

Option

 

a) 600

b) 30

c) 1200

Answer - c) 1200

 

 

Question 163.   Minimum level of supervision for rail dolley working is _____

Option

 

a) JE

b) Gang mate

c) key man

Answer - c) key man

 

 

Question 164.   Detonators can be used in main line for ___ years.   

Option

 

a) 8

b) 17

c) 3

Answer - a) 8

 

 

Question 165.   The caution indicator is provided at ___ m height above rail level.   

Option

 

(a) 1

b) 1.  5

c) 2

Answer - c) 2

 

 

Question 166.   Engineering indicators are used for work of _____ duration.   

Option

 

(a) long

b) short

c) both a & b

Answer - (a) long

 

 

Question 167.   Minimum check rail clearance of 52 kg CMS Xing used for PSC layout is _____ mm.  

Option

 

a) 41

b) 44

c) 51

Answer - a) 41

 

 

Question 168.   The minimum Check rail clearance at Level Crossing is ____ mm

Option

 

(a)  47

(b) 51

(c) 67 m

Answer - (b) 51

 

 

Question 169.   The Permissible throw of switch in new BG turnout is _____ mm.   

Option

 

a) 115

b) 100

c) 95

Answer - a) 115

 

 

Question 170.   Min.   height of FOB at the centre of a BG track in electrified sections is ________mm.   

Option

 

a.   5870

b.   6100

c.   6250

Answer - c.   6250

 

 

Question 171.   Min.   height of a BG high level passenger platform from rail level is _____mm

Option

 

a) 760

b) 840

c) 1035

Answer - a) 760

 

 

Question 172.   SWR can be continued over bridge upto a span of _______ m for unsymmetrical condition.   

Option

 

(a) 13.  3

b) 6.  1

c) 30.  5

Answer - b) 6.  1

 

 

Question 173.   SWR shall not be laid over curved PSC sleeper track with Radius less than _____ metre

Option

 

a) 500

b) 440

c) 875

Answer - b) 440

 

 

Question 174.   Gap Survey is conducted once in ______

Option

 

a) a month

b) a year

c) fortnight

Answer - b) a year

 

 

Question 175.   The fish plated joints of SWR track at level crossing shall not be located with in ____ m from end of Level Crossing.   

Option

 

(a) 3

b) 0

c) 6

Answer - c) 6

 

Question 176.   Gap survey shall be carried out when the rail temperature is in _____ trend only.   

Option

 

(a) rising

b) falling

c) both a & b

Answer - (a) rising

 

 

Question 177.   Profiling and distribution of ballast is carried out by ________ machine

Option

 

a) BRM

b) BCM

c) PQRS

Answer - a) BRM

 

 

Question 178.   ___ number of insertions is given per sleeper by TTM when BG PSC sleeper track is lifted by 50 mm.   

Option

a) 1

b) 2

c) 3

Answer - b) 2

 

 

Question 179.   Motorized trolleys in T-28 machine shall shift the loaded P&C to a maximum of ______ mm to avoid infringements

Option

 

a) 450

b) 300

c) 750

Answer - b) 300

 

 

Question 180.   In smoothening mode of TTM working with four-point lining method, the residual error ratio is 1: ____.   

Option

 

(a) 3.  14

b) 6.  09

c) 1

Answer - b) 6.  09

 

 

Question 181.   The machine that pack 3 sleepers at a time is _____

Option

 

a) Unimat

b) CSM

c) Tamping Express

Answer - c) Tamping Express

 

 

Question 182.   Generally, in BCM working, the machine can screen the ballast for a width of ____ mm

Option

 

a) 3400

b) 2750

c) 4100

Answer - c) 4100

 

 

Question 183.   The tamping cycle for track having other than PSC sleeper is once in ______ years.   

Option

 

(a) 1

b) 2

c) 3

Answer - b) 2

 

 

Question 184.   The dynamic gauge of auxiliary track is ___ mm in PQRS work.   

Option

 

a) 1750

b) 1673

c) 3400

Answer - c) 3400

 

 

Question 185.   Alignment correction can be made when UNIMAT work on _____ track only.   

Option

 

a) main line

b) turnout

c) any

Answer - a) main line

 

 

Question 186.   Design mode of working of Tamping machines cause _________ residual error.   

Option

 

(a) 1: 3.  14

b) 1: 6.  09

c) zero

Answer - a) main line

 

 

Question 187.   ___ based method suitable for isolated attention in track monitoring

Option

 

a) peak

b) SD

c) both a & b

Answer - a) peak

 

 

Question 188.   The BG track with section speed more than 110 kmph having > ___g location require attention

Option

 

a) 0.  15

b) 0.  2

c) 0.  1

Answer - a) 0.  15

 

 

Question 189.   OMS inspection for track with 100 kmph is once in ___ months

Option

 

a) 1

b) 2

c) 4

Answer - b) 2

 

 

Question 190.   Minimum height of a 52 kg rail section for AT welding of rail joints is ____mm

Option

 

a) 156

b) 150

c) 153

Answer - b) 150

 

 

Question 191.   _____ fuel is adopted for AT welding of rail joints.   

Option

(a)  Air - petrol

(b) LPG-OXY

(C) both a & b

Answer - (C) both a & b

 

 

Question 192.   If 880 grade rail has to be welded with 710 grade rail in unavoidable circumstances, welding portion to be used should be ________ grade.   

Option

 

a) 1000

b) 710

c) 880

Answer - c) 880

 

 

Question 193.   During AT welding of rail joints using second hand rails , old AT weld and ____ mm length on either side should be removed.  

Option

 

(a) 85

 (b) 100

 (c) 150

Answer -  (c) 150

 

 

Question 194.   Gap for SKV type of AT weld is ___ mm

Option

(a)  20± 1

(b) 25± 1

(c) 30 ± 1

Answer - (b) 25± 1

 

 

Question 195.   Fastenings of at least ___ sleepers on either side should be made free before welding in the track.   

Option

 

(a)  2

(b) 4

(c) 5

Answer - (c) 5

 

 

Question 196.   At least _____ no.   of supports should be provided on either side for cess welding

Option

 

(a)  5

(b) 2

(c) 10

Answer - (c) 10

 

 

Question 197.   The tolerance for the finished welds of lateral alignment is ______ mm on 10 cm straight edge.   

Option

 

a) +/- 1

b) +/- 0.  5

c) +/- 0.  3

Answer - c) +/- 0.  3

 

 

Question 198.   The railway boundary stones are provided at every ___.   

Option

 

a) 50m

b) change in alignment

c) both a & b

Answer - c) both a & b

 

 

Question 199.   The Stock indent is prepared in _________ number of copies.  

Option

 

a) 2

b) 6

 c) 5

Answer - b) 6

 

 

Question 200.   The accounts stock verification of P.  WAY materials are conducted once in ______ years

Option

a) 1

b) 2

c) 3

 

Answer - a) 1

No comments:

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information.

NOTE: We do not take any responsibility of authencity of Information/News/Videos.

INDEX II

Q Bank - Establishment / Personnel Dept. (82) Q Bank - Electrical Engineering (79) Q Bank - OS / Clerk / Typist (71) Q B Engg (P Way & Work) (67) Q BANK - Operating (62) Group 'B' Exam (60) Q Bank - APO ( Asst. Personnel Officer) (57) QUESTION BANK WITH ANSWER (55) Q B Establishment (47) Q Bank - Goods Guards (45) Q Bank - OHE/TRD/PSI (36) Q B - CIVIL ENGINEERING (AEN) (27) Q B - Welfare Inspector (27) Q BANK - C & W ( Carriage & Wagon ) (26) Q Bank - Account (24) Q BANK - LOCO (23) Q BANK Exam - Station Master (23) Q Bank - Commercial (21) Q Bank - AOM (19) Q BANK - Station Master (18) Q Bank - S & T (14) 1. Syllabus (13) Q Bank - D & AR (Discipline and Appeals Rule) (12) Q Bank - Medical (12) Q Bank - Posts (Civil Engineering & P way) Dept (12) 2. Q Bank - Group D To C (11) INDEX (11) QB - ENGINEERING ( MECHANICAL ) (11) Q Bank - LOCO (Diesel) (9) Q Bank - ACM (Assistant Commercial Manager) (9) Q BANK - Jr Engineer ( Diesel Mechanical ) (8) Q BANK - LOCO (AC) (8) Q Bank - Law Assistant (8) Q Bank - AME/AWM (7) Q Bank - Group D To C (6) Q Bank - Stores (5) RRB EXAM (5) NTPC (4) Q Bank - ADSTE / ASTE (4) Q Bank - AEE (4) Q Bank - CLI (4) Q Bank - General Knowledge (4) Q Bank - Publicity Inspector (4) Q Bank - Rajbhasha (राजभाषा) (4) Question & Answer (4) Q Bank - Appointment On Compassionate Ground Exam (3) Q Bank - Commercial Instructor Exam (3) Q Bank - Engineering (Bridge) (3) Q Bank - IT (3) Q Bank - Protocol Inspector (3) Q Bank - RPF Department (3) Short Notes (3) Q BANK - Jr Engineer ( Mechanical ) (2) Q Bank - C & M (2) Q Bank - Carpenter (2) Q Bank - General English (2) Q Bank - Jr Engineer (Tele) (2) Q Bank - Ministerial Staff (2) Q Bank - Track Machine (2) Q Bank -Section Controler (2) Video (2) ABB (1) FAQ (1) GDCE Exam (1) IRMS (Indian Railway Management Service (1) JUNIOR ENGINEER (Non -AC) GRADE - II (1) Minimum Wages Act (1) Project & Planning (1) Q BANK & Answer - C & W ( Carriage & Wagon ) (1) Q BANK - Shunting Master (1) Q Bank - Instructor (1) Q Bank - AMM (1) Q Bank - All Department (1) Q Bank - Ballast Train Checker (1) Q Bank - CCTC (1) Q Bank - Complaints Inspector (1) Q Bank - GK (Computer) (1) Q Bank - Leave Rule (1) Q Bank - Mason (1) Q Bank - Maths (1) Q Bank - NPS (New Pension Scheme) (1) Q Bank - OS / Clerk Typist (1) Q Bank - Pass Rule (1) Q Bank - Planning Inspector (1) Q Bank - Railway (GK) (1) Q Bank - Stenographer (1) Q Bank - Traffic Costing Inspector (1) Question Bank - Technicians of TLAC Group. (1) Short Notes - Establishment (1) Short Notes - Operating / Traffic (1)