 1. The BDV of transformer oil should be [ b ]


(a) 20 kV 

(b) 30 kV

(c) 40 kV 

(d) 50 kV

Answer : (b) 30 kV

2. The colour of moisten silica gel is [ a ]

(a) Pink 

(b) Blue

(c) Yellow 

(d) Green

Answer :(a) Pink 

3. The material filled in breather of transformer is [ a ]

(a) Silica gel 

(b) Sulphuric acid

(c) SF6 

(d) Mineral oil

Answer :(a) Silica gel 


4. The protective device to indicate the internal fault in a transformer is [ b]

(a)Thermal relay 

(b) Buchholz relay

(c) OVR 

(d) EFR

Answer : (b) Buchholz relay

5. The minimum allowable BDV for transformer oil should stand for [ d ]

(a)15 sec 

(b) 30 sec

(c) 45 sec 

(d) 60 sec

Answer : (d) 60 sec


6. While testing transformer oil the gap between electrodes is kept at a distance of [ d ]

(a) 1 mm 

(b) 2 mm

(c) 3 mm 

(d) 4 mm

Answer : (d) 4 mm



7 Core of a transformer is made up of [ d ]

(a) Aluminium 

(b) Carbon

(c) Lead 

(d) Silicon steel.

Answer :(d) Silicon steel.


8 Which of the following is not the function of a transformer oil [ d ]

(a) Cooling of primary Coils

(b) Cooling of secondary coils.

(c) Providing additional insulation.

(d) Providing inductive coupling.

Answer :(d) Providing inductive coupling.


9 For a transformer, the condition for maximum efficiency is [ c ]

(a) Hysteresis loss = eddy current loss

(b) Core loss = hysteresis loss

(c) Copper loss = Iron loss

(d) Total loss = 2/3 copper loss.

Answer :(c) Copper loss = Iron loss


10 Transformer oil shall be free from [ d ]

(a) Odour 

(b) Gases 

(c) Temperature 

(d) Moisture.

Answer :(d) Moisture.


11 The power factor in a transformer [ d ]

(a) Is always unity

(b) Is always leading

(c) Is always lagging

(d) Depends on power factor of load.

Answer :(d) Depends on power factor of load.


12 The short circuit test of a transformer gives [ a]

(a) Copper loss at full load

(b) Copper loss at half load

(c) Iron loss at any load

(d) Sum of iron loss and copper load.

Answer :(a) Copper loss at full load


13 The open circuit test of transformer determines [ a ]

(a) Iron loss

(b) Copper loss at full load

(c) Copper loss at half load

(d) Total losses.

Answer :(a) Iron loss


14 The type of oil, which is suitable as transformer oil is [ c ]

(a) Crude oil 

(b) Organic oil

(c) Mineral oil 

(d) Animal oil.

Answer :(c) Mineral oil 


15 A step up transformer increases [ c ]

(a) Power 

(b) Current

(c) Voltage 

(d) Frequency.

Answer :(c) Voltage 


16 Which test is conducted on all transformers in a manufacturing concern [ a ]

(a) Routine test 

(b) Type test

(c) Special test 

(d) All above

Answer :(a) Routine test 


17 The colour of fresh dielectric oil for a transformer [ d ]

(a) Pale yellow 

(b) Dark brown

(c) White to grey 

(d) Colour less

Answer :(d) Colour less


18 The ratio of kW to kVA is known as [ b ]

(a) Voltage regulation 

(b) power factor

(c) Transformation ratio 

(d) None above

 Answer : (b) power factor


19 Core lifting of a transformer is done after a period of [ c ]

(a) 3 yrs. 

(b) 4 yrs.

(c) 5 yrs.

 (d) 6 yrs.

Answer : (c) 5 yrs.


20 The purpose of conservator tank in a transformer is to [ c ]

(a) Monitor the oil level 

(b) Top up the oil level

(c) Both a & b above 

(d) None of the above.

Answer :(c) Both a & b above 


21 Transformers placed in a room enclosed from all the four sides, the minimum spacing between the walls and the transformer should be [d]

(a) 0.5 m 

(b) 0.75 m 

(c) 1 m 

(d) 1.25 m

Answer :(d) 1.25 m


22 . For indoor installation the minimum clearance between the highest point of the conservator tank to the ceiling of the transformer room should be [ b ]

(a)0.25 m 

(b) 0.5 m

(c) 0.75 m 

(d) 1 m

Answer :(b) 0.5 m


23 At an atmospheric temperature of 45 deg C and keeping in view the working condition, the winding temperature of the transformer should not exceed [ b ]

(a) 80 deg C 

(b) 95 deg C

(c) 110 degC 

(d) 130 deg C

Answer :(b) 95 deg C


24. Which of the following does not change in a transformer? [ c ]

a. Current 

b. Voltage

c. Frequency 

d. All of the above

Answer :c. Frequency 

25. In a transformer the energy is conveyed from primary to secondary [ c ]

a. through cooling coil 

b. through air

c. by the flux 

d. none of the above

Answer :c. by the flux 


26. A transformer core is laminated to [ b ]

a. reduce hysteresis loss 

b. reduce eddy current losses

c. reduce copper losses 

d. reduce all above losses

Answer :b. reduce eddy current losses

27. The path of a magnetic flux in a transformer should have [ d ]

a. high resistance 

b. high reluctance

c. low resistance

d. low reluctance

Answer :d. low reluctance


28. No-load test on a transformer is carried out to determine [ c ]

a. copper loss 

b. magnetizing current

c. magnetizing current and loss 

d. efficiency of the transformer

Answer :c. magnetizing current and loss 

29. The dielectric strength of transformer oil is expected to be [ b ]

a. 1 kV 

b. 33 kV 

c. 100 kV 

d. 330 kV

Answer :b. 33 kV 


30. The efficiency of a transformer will be maximum when [ d ]

a. copper losses = hysteresis losses

b. hysteresis losses = eddy current losses

c. eddy current losses = copper losses

d. copper losses = iron losses

Answer :d. copper losses = iron losses


31. No-load current in a transformer [ a ]

a. lags behind the voltage by about 75° 

b. leads the voltage by about 75°

c. lags behind the voltage by about 15° 

d. leads the voltage by about 15°

Answer :a. lags behind the voltage by about 75° 


32. The purpose of providing an iron core in a transformer is to [ c ]

a. provide support to windings 

b. reduce hysteresis loss

c. decrease the reluctance of the magnetic path d. reduce eddy current losses

Answer :c. decrease the reluctance of the magnetic path d. reduce eddy current losses


33. Which of the following is not a part of transformer installation? [ d ]

a. Conservator 

b. Breather 

c. Buchholz relay 

d. Exciter

Answer :d. Exciter


34. While conducting short circuit test on a transformer the following side is Short circuited [ b ]

a. High voltage side 

b. Low voltage side

c. Primary side 

d. Secondary side

Answer :b. Low voltage side


35. In the transformer following winding has got more cross-section area [ a ]

a. low voltage winding 

b. High voltage winding

c. primary winding 

d. secondary winding

Answer :a. low voltage winding 


36. A transformer transforms [ c ]

a. voltage 

b. current 

c. power

d. frequency

Answer :c. power


37. A transformer cannot raise or lower the voltage of a D.C. supply because [ c ]

a. there is no need to change the D.C. voltage

b. a D.C. circuit has more losses

c. Faraday’s laws of electromagnetic induction are not valid since the rate of change of flux is zero

d. none of the above

Answer :c. Faraday’s laws of electromagnetic induction are not valid since the rate of change of flux is zero


38. Primary winding of a transformer [ c ]

a. is always a low voltage winding 

b. is always a high voltage winding

c. could either be a low or high voltage 

d. none of the above winding

Answer :c. could either be a low or high voltage 


39. Which winding in a transformer has more number of turns? [ b ]

a. Low voltage winding 

b. High voltage winding

c. Primary winding 

d. Secondary winding

Answer :b. High voltage winding


40. Efficiency of a power transformer is of the order of [ b ]

a. 100 percent 

b. 98 percent

c. 50 percent 

d. 25 percent

Answer :b. 98 percent


41. A common method of cooling a power transformer is [ c ]

a.natural air cooling 

b. air blast cooling

c. oil cooling 

d. any of the above

Answer :c. oil cooling 


42. In a transformer routine efficiency depends upon [ d ]

a. supply frequency 

b. load current

c. power factor of load 

d. both (b) and (c)

Answer :d. both (b) and (c)

43. The maximum efficiency of a distribution transformer is [ ]

a. at no load 

b. at 50% full load

c. at 80% full load 

d. at full load

Answer :a. at no load 


44. Transformer breaths in when [ b]

a. load on it increases 

b. load on it decreases

c. load remains constant 

d. none of the above

Answer :b. load on it decreases


45. No-load current of a transformer has [ d ]

a. has high magnitude and low power factor

b. has high magnitude and high power factor

c. has small magnitude and high power factor

d. has small magnitude and low power factor

Answer :d. has small magnitude and low power factor


46. Spacers are provided between adjacent coils [ a ]

a. to provide free passage to the cooling oil

b. to insulate the coils from each other

c. both (a) and (b)

d. none of the above

Answer : a. to provide free passage to the cooling oil


47. In a transformer the tappings are generally provided on [ d ]

a. primary side 

b. secondary side

c. low voltage side 

d. high voltage side

Answer :d. high voltage side


48. The chemical used in breather for transformer should have the quality of [ b]

a. ionizing air 

b. absorbing moisture

c. cleaning the transformer oil 

d. cooling the transformer oil

Answer :b. absorbing moisture


49. The chemical used in breather is [ d ]

a. asbestos fibre 

b. silica sand

c. sodium chloride 

d. silica gel

Answer :d. silica gel

50. The transformer ratings are usually expressed in terms of [ d]

a. Volts 

b. amperes

c. kW 

d. kVA

Answer : d. kVA


51. Material used for construction of transformer core is usually [ d ]

a. Wood 

b. copper

c. Aluminium 

d. silicon steel

Answer :d. silicon steel

52. The thickness of lamination used in a transformer is usually [ a ]

a. 0.4mm to 0.5 mm 

b. 4 mm to 5 mm

c. 14mm to 15mm 

d. 25mm to 40 mm

Answer :a. 0.4mm to 0.5 mm 

53. The function of conservator in a transformer is [ d ]

a. to protect against internal fault

b. to reduce copper as well as core losses

c. to cool the transformer oil

d. to take care of the expansion and contraction of transformer oil due to variation of temperature of surroundings

Answer :d. to take care of the expansion and contraction of transformer oil due to variation of temperature of surroundings


54. A Buchholz relay can be installed on [ d ]

a. auto-transformers 

b. air-cooled transformers

c. welding transformers 

d. oil cooled transformers

Answer :d. oil cooled transformers

55. Buchholz’s relay gives warning and protection against [ a ]

a. electrical fault inside the transformer itself

b. electrical fault outside the transformer in outgoing feeder

c. for both outside and inside faults

d. none of the above

Answer :a. electrical fault inside the transformeritself


56. The transformer laminations are insulated from each other by [ b ]

a. mica strip 

b. thin coat of varnish

c. paper 

d. any of the above

Answer :b. thin coat of varnish


57. During open circuit test of a transformer [ a ]

a. primary is supplied rated voltage

b. primary is supplied full-load current

c. primary is supplied current at reduced voltage

d. primary is supplied rated kVA

Answer :a. primary is supplied rated voltage


58. Open circuit test on transformers is conducted to determine [ c ]

a. hysteresis losses 

b. copper losses

c. core lossesd. 

d. eddy current losses

Answer :c. core lossesd. 


59. Short circuit test on transformers is conducted to determine [ b ]

a. hysteresis losses 

b. copper losses

c. core losses 

d. eddy current losses

Answer :b. copper losses


60. The function of breather in a transformer is [ d ]

a. to provide oxygen inside reduced load

b. to cool the coils during reduced load

c. to cool the transformer oil

d. to arrest flow of moisture when outside air enters the transformer

Answer :d. to arrest flow of moisture when outside air enters the transformer


61. The secondary winding of which of the following transformers is always kept closed? [ d ]

a. Step-up transformer 

b. Step-down transformer

c. Potential transformer 

d. Current transformer

Answer :d. Current transformer


62. For a transformer, operating at constant load current, maximum efficiency will occur at [d]

a. 0.8 leading power factor 

b. 0.8 lagging power factor

c. zero power factor 

d. unity power factor

Answer :d. unity power factor


63. Which of the following protection is normally not provided on small distribution transformers?[ b ]

a. Over-fluxing protection 

b. Buchholz relay

c. Over-current protection 

d. All of the above

Answer :b. Buchholz relay


64. Which of the following acts as a protection against high voltage surges due to lightning and switching? [ a]

a. Horn gaps 

b. Thermal overload relays

c. Breather 

d. Conservator

Answer :a. Horn gaps 


65. Which of the following parts of a transformer is visible from outside? [ a ]

a. Bushings 

b. Core

c. Primary winding 

d. Secondary winding

Answer :a. Bushings 


66. The noise produced by a transformer is termed as [ b ]

a. zoom 

b. hum

c. Ringing 

d. buzz

Answer :b. hum


67. Which of the following loss in a transformer is zero even at full load? [ b ]

a. core loss 

b. friction loss

c. eddy current loss 

d. hysteresis loss

Answer :b. friction loss


68. If a transformer is continuously operated the maximum temperature rise will occur in [ b ]

a. Core 

b. windings

c. Tank d. any of the above

Answer :b. windings


69. An open-circuit test on a transformer is conducted primarily to measure [ c]

a. Insulation Resistance 

b. Copper loss

c. Core loss 

d. Total loss

Answer :c. Core loss 


70. A no-load test is performed on a transformer to determine [ d ]

a. Core loss 

b. Copper loss

c. Efficiency 

d. Magnetising current and loss

Answer :d. Magnetising current and loss

No comments:

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information.

NOTE: We do not take any responsibility of authencity of Information/News/Videos.

INDEX II

Q Bank - Establishment / Personnel Dept. (82) Q Bank - Electrical Engineering (79) Q Bank - OS / Clerk / Typist (71) Q B Engg (P Way & Work) (67) Q BANK - Operating (62) Group 'B' Exam (60) Q Bank - APO ( Asst. Personnel Officer) (57) QUESTION BANK WITH ANSWER (55) Q B Establishment (47) Q Bank - Goods Guards (45) Q Bank - OHE/TRD/PSI (36) Q B - CIVIL ENGINEERING (AEN) (27) Q B - Welfare Inspector (27) Q BANK - C & W ( Carriage & Wagon ) (26) Q Bank - Account (24) Q BANK - LOCO (23) Q BANK Exam - Station Master (23) Q Bank - Commercial (21) Q Bank - AOM (19) Q BANK - Station Master (18) Q Bank - S & T (14) 1. Syllabus (13) Q Bank - D & AR (Discipline and Appeals Rule) (12) Q Bank - Medical (12) Q Bank - Posts (Civil Engineering & P way) Dept (12) 2. Q Bank - Group D To C (11) INDEX (11) QB - ENGINEERING ( MECHANICAL ) (11) Q Bank - LOCO (Diesel) (9) Q Bank - ACM (Assistant Commercial Manager) (9) Q BANK - Jr Engineer ( Diesel Mechanical ) (8) Q BANK - LOCO (AC) (8) Q Bank - Law Assistant (8) Q Bank - AME/AWM (7) Q Bank - Group D To C (6) Q Bank - Stores (5) RRB EXAM (5) NTPC (4) Q Bank - ADSTE / ASTE (4) Q Bank - AEE (4) Q Bank - CLI (4) Q Bank - General Knowledge (4) Q Bank - Publicity Inspector (4) Q Bank - Rajbhasha (राजभाषा) (4) Question & Answer (4) Q Bank - Appointment On Compassionate Ground Exam (3) Q Bank - Commercial Instructor Exam (3) Q Bank - Engineering (Bridge) (3) Q Bank - IT (3) Q Bank - Protocol Inspector (3) Q Bank - RPF Department (3) Short Notes (3) Q BANK - Jr Engineer ( Mechanical ) (2) Q Bank - C & M (2) Q Bank - Carpenter (2) Q Bank - General English (2) Q Bank - Jr Engineer (Tele) (2) Q Bank - Ministerial Staff (2) Q Bank - Track Machine (2) Q Bank -Section Controler (2) Video (2) ABB (1) FAQ (1) GDCE Exam (1) IRMS (Indian Railway Management Service (1) JUNIOR ENGINEER (Non -AC) GRADE - II (1) Minimum Wages Act (1) Project & Planning (1) Q BANK & Answer - C & W ( Carriage & Wagon ) (1) Q BANK - Shunting Master (1) Q Bank - Instructor (1) Q Bank - AMM (1) Q Bank - All Department (1) Q Bank - Ballast Train Checker (1) Q Bank - CCTC (1) Q Bank - Complaints Inspector (1) Q Bank - GK (Computer) (1) Q Bank - Leave Rule (1) Q Bank - Mason (1) Q Bank - Maths (1) Q Bank - NPS (New Pension Scheme) (1) Q Bank - OS / Clerk Typist (1) Q Bank - Pass Rule (1) Q Bank - Planning Inspector (1) Q Bank - Railway (GK) (1) Q Bank - Stenographer (1) Q Bank - Traffic Costing Inspector (1) Question Bank - Technicians of TLAC Group. (1) Short Notes - Establishment (1) Short Notes - Operating / Traffic (1)