SEARCH

Q Bank & Answer - Electrical Engineer - ERRU

01. Voltage regulation of alternator with ERRU for all capacities of alternator. [ c]

 a)+/-5% 

b)+/-3% 

c)+/-2% 

d) None

Answer - c)+/-2% 


02. Voltage ripples of output supply with ERRU should be less than [ a ]

a)2% 

b)5% 

c)15%

 d)none

Answer -  a)2% 

03. ISO pack power diode modulars are used for converting [ a ]

a)AC to DC 

b) DC to AC

 c) both A&B 

d) none

Answer - a)AC to DC 

 
04. The advantage of ISO pack power modules are [ d ]

a) Directly can mount on heat sink

b) two diode combined unit

c) Small in size

 d) all of the above

Answer -  d) all of the above


05. The ERRU shall have the following protection [ d ]

 a) Over voltage/surge protection

 b) DC output short circuit protection

 c) Over charging current limit protection 

d) all of the above

Answer -   d) all of the above


06. UVC used in ERRU must be [ a ]

a) Suitable to work with all capacities 

b) suitable to work all makes

c) Both A&B 

d) none

Answer -   a) Suitable to work with all capacities 


07. The over voltage setting of OVP with ERRU should be set at [ a ]

 a)140-145V 

b)125-130V 

c)135-140V 

d)none

Answer -   a)140-145V 


08. The battery charging current limit with 4.5 KW ERRU is to be set at [ a ]

 a) 24A +/-2A 

b)12A +/-2A 

c)36A +/-2A 

d) none

Answer -  a) 24A +/-2A 


09. The battery charging current limit with 25kw ERRU when both alternators are paralleled is to be set at [ a ]

a) 110A +/-5A 

b)220A +/-5A 

c)220A +/-10A 

d)none

Answer - a) 110A +/-5A 


10. OVP provided with ERRU shall latch before output voltage reaches to [ c ]

 a) 145V 

b) 150V 

c) 135V+/-2V 

d) none

Answer -  c) 135V+/-2V 


11. Hall senses are used to sense [ c ]

a) Total alternator load current 

b) battery charging current

c) both A&B

 d) none

Answer -  c) both A&B


12. OVP is provided in ERRU for the purpose of [ c ]

a) To arrest the over voltage

b) latch the output voltage 90V for working lights and fans

c) Both A&B

d) none

Answer -  c) Both A&B


13. PWM stands for [ a ]

 a) Pulse width modulation 

b) phase width modulation

 c) both A&B 

d) none 

Answer -  a) Pulse width modulation 


14. EEPROM stands for [ a ]

a) Electrically erasable programmable read only memory

b) Electronically erasable programmable read only memory

c) Both A&B 

d) none

Answer - a) Electrically erasable programmable read only memory


15. SMPS stands for [ a ]

a) switch mode power supply 

b) single mode power supply

c) sweep mode power supply 

d) none

Answer - a) switch mode power supply 


16. IGBT stands for [ a ]

a) Insulated gate bipolar transistor 

b) isolated gate bipolar transistor

c) Both A&B 

d) none 

Answer -  a) Insulated gate bipolar transistor 

No comments:

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information.

NOTE: We do not take any responsibility of authencity of Information/News/Videos.

INDEX II

Q Bank - Establishment / Personnel Dept. (82) Q Bank - Electrical Engineering (79) Q Bank - OS / Clerk / Typist (71) Q B Engg (P Way & Work) (67) Q BANK - Operating (61) Group 'B' Exam (60) Q Bank - APO ( Asst. Personnel Officer) (57) QUESTION BANK WITH ANSWER (55) Q B Establishment (47) Q Bank - Goods Guards (45) Q Bank - OHE/TRD/PSI (36) Q B - CIVIL ENGINEERING (AEN) (27) Q B - Welfare Inspector (27) Q BANK - C & W ( Carriage & Wagon ) (25) Q Bank - Account (24) Q BANK - LOCO (23) Q BANK Exam - Station Master (23) Q Bank - Commercial (21) Q Bank - AOM (19) Q BANK - Station Master (18) Q Bank - S & T (14) 1. Syllabus (12) Q Bank - D & AR (Discipline and Appeals Rule) (12) Q Bank - Medical (12) Q Bank - Posts (Civil Engineering & P way) Dept (12) 2. Q Bank - Group D To C (11) INDEX (11) QB - ENGINEERING ( MECHANICAL ) (11) Q Bank - LOCO (Diesel) (9) Q Bank - ACM (Assistant Commercial Manager) (9) Q BANK - Jr Engineer ( Diesel Mechanical ) (8) Q BANK - LOCO (AC) (8) Q Bank - Law Assistant (8) Q Bank - AME/AWM (7) Q Bank - Group D To C (6) Q Bank - Stores (5) RRB EXAM (5) NTPC (4) Q Bank - ADSTE / ASTE (4) Q Bank - CLI (4) Q Bank - General Knowledge (4) Q Bank - Publicity Inspector (4) Q Bank - Rajbhasha (राजभाषा) (4) Question & Answer (4) Q Bank - AEE (3) Q Bank - Appointment On Compassionate Ground Exam (3) Q Bank - Commercial Instructor Exam (3) Q Bank - Engineering (Bridge) (3) Q Bank - IT (3) Q Bank - Protocol Inspector (3) Q Bank - RPF Department (3) Short Notes (3) Q BANK - Jr Engineer ( Mechanical ) (2) Q Bank - C & M (2) Q Bank - Carpenter (2) Q Bank - General English (2) Q Bank - Jr Engineer (Tele) (2) Q Bank - Ministerial Staff (2) Q Bank -Section Controler (2) Video (2) ABB (1) FAQ (1) GDCE Exam (1) IRMS (Indian Railway Management Service (1) JUNIOR ENGINEER (Non -AC) GRADE - II (1) Minimum Wages Act (1) Project & Planning (1) Q BANK & Answer - C & W ( Carriage & Wagon ) (1) Q Bank - Instructor (1) Q Bank - AMM (1) Q Bank - All Department (1) Q Bank - Ballast Train Checker (1) Q Bank - CCTC (1) Q Bank - Complaints Inspector (1) Q Bank - GK (Computer) (1) Q Bank - Leave Rule (1) Q Bank - Mason (1) Q Bank - Maths (1) Q Bank - NPS (New Pension Scheme) (1) Q Bank - OS / Clerk Typist (1) Q Bank - Pass Rule (1) Q Bank - Planning Inspector (1) Q Bank - Railway (GK) (1) Q Bank - Stenographer (1) Q Bank - Track Machine (1) Q Bank - Traffic Costing Inspector (1) Question Bank - Technicians of TLAC Group. (1) Short Notes - Establishment (1) Short Notes - Operating / Traffic (1)