1 Provision of rebate by state electricity authority is applicable if the power factor is kept above [ c ]
(a) 0.9
(b) 0.92
(c) 0.95
(d) 0.98
Answer - (c) 0.95
2. Penalty is imposed by state electricity authority if the power factor is below [ a ]
(a) 0.9
(b) 0.92
(c) 0.95
(d) 0.98
Answer - (a) 0.9
3 Electric energy charges from the railway employees residing in railway colonies are at [d]
(a) Flat rate
(b) Fixed rate
(c) Average consumption
(d) The rate that of local supply authority
Answer - (d) The rate that of local supply authority
4 Electric energy charges from the staff/ teachers of Kendriya Vidhyalaya residing in railway colonies is at [ d ]
(a) Flat rate
(b) Fixed rate
(c) Average consumption
(d) The rate applicable to railway employees
Answer - (d) The rate applicable to railway employees
5 Electric energy charges from the social welfare organizations such as railway institute, community halls, clubs, etc. is at [ d ]
(a)Flat rate
(b)Fixed rate
(c)Average consumption
(d)The rate applicable to railway employee subject to maximum limit of consumption.
Answer - (d)The rate applicable to railway employee subject to maximum limit of consumption.
6 Electric energy charges from the religious buildings (electric supply fed by railway) such as temples. Mosque etc is at [ d ]
(a) Flat rate
(b) Fixed rate
(c) Average consumption
(d) The rate that of local supply authority
Answer - (d) The rate that of local supply authority
7 Per day charges from officers on duty (entitled to 1st class AC travel) for occupation of air conditioned accommodation on railway rest house is Rs. [ c ]
(a) 3
(b) 5
(c) 6
(d) 7
Answer - (c) 6
8 Per day charges from officers on leave (entitled to 1st class AC travel) for occupation of air conditioned accommodation on railway rest house is prescribed room rent plus Rs . [ c ]
(a) 3
(b) 5
(c) 6
(d) 7
Answer - (c) 6
9 Per day charges from officers on duty (entitled to 1st class AC travel) for occupation of air conditioned accommodation on railway rest house during winter season is Rs. [ d ]
(a) 3
(b) 5
(c) 6
(d) No
Answer - (d) No
10 The firms dealing with coin operated person weighing machines has to deposit security money equivalent to [ a ]
(a) One month electric charges
(b)Two month electric charges
(c) Three month electric charges
(d) No charges.
Answer - (a) One month electric charges
11 The private parties applying for electric connection from railways has to deposit security money equivalent to [ c ]
(a) One month electric charges
(b) Two month electric charges
(c) Three month electric charges
(d) No charges.
Answer - (c) Three month electric charges
12 As per Railway Board recommendations, following are to be connected with DG set supply [ d ]
(a) Vacuum testing plants
(b) Water coolers on platforms
(c) Hospital with operation theatre
(d) All of the above.
Answer - (d) All of the above.
13 As per Railway Board recommendations, the stations/ halts should be electrified, where the electric supply is available within [ a ]
(a) 1 km
(b) 1.5 km
(c) 2 km
(d) 2.5 km
Answer - (a) 1 km
14 The porters rest centres are treated as [ a ]
(a) Service building
(b) Private building
(c) Passenger amenity
(d) None of the above
Answer - (a) Service building
15 As per Indian Electricity Act, penalty against unauthorised electricity connection is [ a ]
(a) Imprisonment up to 3 yrs and fine up to Rs. 1000/-
(b) Imprisonment up to 2 yrs and fine up to Rs. 1000/-
(c) Imprisonment up to 3 yrs and fine up to Rs. 1500/-
(d) Imprisonment up to 2 yrs and fine up to Rs. 1500/-
Answer - (a) Imprisonment up to 3 yrs and fine up to Rs. 1000/-
16 Number of geysers that can be provided in officer’s flat (on special request) [ a ]
(a) 1
(b) 2
(c) 3
(d) 4
Answer - (a) 1
17 Number of geysers that can be provided in the GM’s bungalow is [ b ]
(a) 1
(b) 2
(c) 3
(d) 4
Answer - (b) 2
18 The railway stations at zonal headquarters and state capitals are classified as of category
(a) A
(b) B
(c) C
(d) D
Answer - (a) A
19 The railway stations at divisional headquarters and district headquarters are classified as of category [ b ]
(a) A
(b) B
(c) C
(d) D
Answer - (b) B
20 As per Railway Board recommendations, the light fittings for platform on category A and B stations are [ c ]
(a) 1 x 36 W FL tube
(b) 2 x 36 W HPSV
(c) 1 x 70 W HPSV
(d) 2 x 36 W HPSV
Answer - (c) 1 x 70 W HPSV
21 As per Railway Board recommendations, the light fittings for platform on category C stations are [ a ]
(a) 1 x 36 W FL tube
(b) 2 x 36 W HPSV
(c) 1 x 70 W HPSV
(d) 2 x 36 W HPSV
Answer - (a) 1 x 36 W FL tube
22 As per Railway Board recommendations, the light fittings for ASM office, SM office, enquiry and PRS on category A and B stations are [ a ]
(a) 2 x 36 W mirror optic FL tube
(b) 4 x 36 W mirror optic FL tube
(c) 2 x 36 W box type FL tube
(d) 4 x 36 W box type FL tube
Answer - (a) 2 x 36 W mirror optic FL tube
23 As per Railway Boards recommendations, the light fittings in station approach and car parks are [ a ]
(a) 1 x 70 W HPSV
(b) 2 x 70 W HPSV
(c) 1 x 40 W Box type
(d) 2 x 40 W box type
Answer - (a) 1 x 70 W HPSV
24 As per Railway Board recommendations, on platform having width of 9-6 m, fannage should be provided in [ a ]
(a) 1 row
(b) 2 rows
(c) 3 rows
(d) 4 rows
Answer - (a) 1 row
25 As per Railway Board recommendations, on platform having width more than 9 m, fannage should be provided in [ b ]
(a) 1 row
(b) 2 rows
(c) 3 rows
(d) 4 rows
Answer - (b) 2 rows
26 As per Railway Board recommendations, the sweep of fans provided on platforms should be [ d ]
(a) 800 mm
(b) 1200 mm
(c) 1500 mm
(d) 1800 mm
Answer - (d) 1800 mm
27 As per Railway Board recommendations, the sweep of fans provided in offices, waiting hall etc. should be [ c ]
(a) 800 mm
(b) 1200 mm
(c) 1500 mm
(d) 1800 mm
Answer - (c) 1500 mm
28 As per Railway Board recommendations, the sweep of fans provided in retiring rooms on each bed should be [ b ]
(a) 800 mm
(b) 1200 mm
(c) 1500 mm
(d) 1800 mm
Answer - (b) 1200 mm
29 At stations where neither electrical supervisor nor engineering supervisor is headquartered, the upkeep of pumps in water supply system is under [ b ]
(a) S & T supervisor
(b) Station Master
(c) Gangman
(d) Pointsman
Answer - (b) Station Master
30 State Electricity Board charges Electricity Duty against selling electricity to railways amounting Rs. [ d ]
(a) 10,000/-
(b) 50,000/-
(c) 75,000/-
(d) No
Answer - (d) No
31 Railway Board has recommended that locations where HPSV lamps affect the colour light signalling should be replaced by [ c ]
(a)Mercury Vapour Lamps
(b)FL tube fittings
(c)Any of A & B
(d)No such recommendation has been made.
Answer - (c)Any of A & B
32 The maintenance of water coolers donated by private parties is to be done by [ b ]
(a) The donating party
(b) Railways
(c) On contract
(d) Any of the above.
Answer - (b) Railways
33 The electrical energy consumption on water coolers donated by private parties are to be borne by [ b ]
(a) The donating party
(b) Railways
(c) SEB
(d) Through collection from public
Answer - (b) Railways
34 The Railway Board has recommended to provide water coolers at stations with _____ passengers (inward & outward) per day [ b ]
(a) 500
(b) 1000
(c) 1500
(d) 2000
Answer - (b) 1000
No comments: