6.1 In AC traction, minimum height of contact wire under ROB/FOB from rail level to permit “C”class ODC
(a) 4.92 m 
(b) 4.80 m 
(c) 4.65 m 
(d) 5.03 m
Answer - (a) 4.92 m 

6.2 In AC traction, height of contact wire at support from rail level (regulated OHE) with 50 mmpre sag in contact wire is
(a) 5.50 m
 (b) 5.55 m 
(c) 5.60 m 
(d) 5.65 m
Answer -  (b) 5.55 m 

6.3 In AC traction, height of contact wire at support from rail level (regulated OHE) with 100 mmpre sag in contact wire is
(a) 5.50 m 
(b) 5.55 m
(c) 5.60 m 
(d) 5.75 m
Answer - (c) 5.60 m 

6.4 In AC traction, height of contact wire from rail level in Car shed is
(a) 5.60 m 
(b) 5.65 m 
(c) 5.75 m 
(d)5.80 m
Answer - (d)5.80 m

6.5 In AC traction, normal height of the catenary wire at support from rail level (regulated OHE)with 100 mm pre sag in contact wire is about
(a) 7.20 m 
(b) 7.75 m 
(c) 7.25 m 
(d) 7.45 m
Answer - (a) 7.20 m 

6.6 In AC traction, height of contact wire (unregulated OHE) for 40-centigrade to 650 degreecentigrade area is
(a) 5.5 m 
(b) 5.55 m 
(c) 5.6 m 
(d) 5.75 m
Answer - (d) 5.75 m

6.7 In AC traction, height of contact wire (unregulated OHE) for 160 centigrade to 650 centigradearea is
(a) 5.55 m 
(b) 5.6 m 
(c) 5.65 m 
(d) 5.75 m
Answer - (c) 5.65 m 

6.8 In AC traction , height of termination of regulated OHE is
(a) 6.45 m
(b) 6.75 m 
(c) 6.95 m 
(d) 7.25 m
Answer - (b) 6.75 m 

6.9 In AC traction, height of termination of unregulated OHE is
(a) 6.75 m 
(b) 6.8 m 
(c) 6.95 m 
(d) 7.2 m
Answer - (c) 6.95 m 

146.10 In AC traction, height of catenary termination for split anchor (regulated OHE) is
(a) 6.75 m 
(b) 6.95 m 
(c) 7.15 m 
(d) 7.25 m
Answer - (a) 6.75 m 

6.11 In AC traction, height of catenary termination for split anchor (unregulated OHE) is
(a) 6.75 m 
(b) 6.95 m 
(c) 7.15 m 
(d) 7.25 m
Answer - (b) 6.95 m 

6.12 In AC traction, height of contact termination for split anchor (regulated OHE) is
(a) 6.25 m 
(b) 6.45 m 
(c) 6.75 m 
(d) 6.95 m
Answer - (a) 6.25 m 

6.13 In AC traction, height of contact termination for split anchor (unregulated OHE) is
(a) 6.25 m 
(b) 6.45 m 
(c) 6.75 m 
(d) 6.95 m
Answer - (b) 6.45 m 

6.14 In AC traction, height of termination of return conductor is
(a) 6.75 m 
(b) 6.95 m 
(c) 7.25 m 
(d) 7.45 m
Answer -(a) 6.75 m 
 
6.15 At level crossing gate, maximum height of rail height gauge from the road surface is
(a) 4.38 m 
(b) 4.67 m 
(c) 4.80 m 
(d) 4.45 m
Answer - (b) 4.67 m 

6.16 At level crossing gate, minimum distanceof rail height gauge from the nearest track should be
(a) 4 m 
(b) 8 m 
(c) 10 m 
(d) 12 m
Answer - (b) 8 m 

6.17 In AC traction, height of contact wire at level crossing from rail level (regulated OHE)
(a) 5.50 m 
(b) 5.55 m 
(c) 5.60 m 
(d) 5.65 m
Answer - (a) 5.50 m 

6.18 In AC traction, tolerance in height of catenary wire from rail level at support is ( As perRDSO latter no.TI/OHE/GA/3013 dated 14.05.13
(a) Zero 
(b) ± 50 mm 
(c) ± 20 mm 
(d) ) ± 10 mm
Answer - (b) ± 50 mm 

6.19 Tolerance of catenary wire height is (As per RDSO latter no. TI/OHE/GA/2013 dated14.05.1013)(a) ± 30 mm 
(b) ± 50 mm 
(c) ± 10 mm 
(d) Zero
Answer - (b) ± 50 mm 

6.20 In AC traction , the minimum height of contact wire is
(a) 4.69 m 
(b) 4.79 m 
(c) 4.92 m 
(d) 4.89 m
Answer - (a) 4.69 m 

No comments:

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information.

NOTE: We do not take any responsibility of authencity of Information/News/Videos.

INDEX II

Q Bank - Establishment / Personnel Dept. (82) Q Bank - Electrical Engineering (79) Q Bank - OS / Clerk / Typist (71) Q B Engg (P Way & Work) (67) Q BANK - Operating (61) Group 'B' Exam (60) Q Bank - APO ( Asst. Personnel Officer) (57) QUESTION BANK WITH ANSWER (55) Q B Establishment (47) Q Bank - Goods Guards (45) Q Bank - OHE/TRD/PSI (36) Q B - CIVIL ENGINEERING (AEN) (27) Q B - Welfare Inspector (27) Q BANK - C & W ( Carriage & Wagon ) (25) Q Bank - Account (24) Q BANK - LOCO (23) Q BANK Exam - Station Master (23) Q Bank - Commercial (21) Q Bank - AOM (19) Q BANK - Station Master (18) Q Bank - S & T (14) 1. Syllabus (12) Q Bank - D & AR (Discipline and Appeals Rule) (12) Q Bank - Medical (12) Q Bank - Posts (Civil Engineering & P way) Dept (12) 2. Q Bank - Group D To C (11) INDEX (11) QB - ENGINEERING ( MECHANICAL ) (11) Q Bank - LOCO (Diesel) (9) Q Bank - ACM (Assistant Commercial Manager) (9) Q BANK - Jr Engineer ( Diesel Mechanical ) (8) Q BANK - LOCO (AC) (8) Q Bank - Law Assistant (8) Q Bank - AME/AWM (7) Q Bank - Group D To C (6) Q Bank - Stores (5) RRB EXAM (5) NTPC (4) Q Bank - ADSTE / ASTE (4) Q Bank - CLI (4) Q Bank - General Knowledge (4) Q Bank - Publicity Inspector (4) Q Bank - Rajbhasha (राजभाषा) (4) Question & Answer (4) Q Bank - AEE (3) Q Bank - Appointment On Compassionate Ground Exam (3) Q Bank - Commercial Instructor Exam (3) Q Bank - Engineering (Bridge) (3) Q Bank - IT (3) Q Bank - Protocol Inspector (3) Q Bank - RPF Department (3) Short Notes (3) Q BANK - Jr Engineer ( Mechanical ) (2) Q Bank - C & M (2) Q Bank - Carpenter (2) Q Bank - General English (2) Q Bank - Jr Engineer (Tele) (2) Q Bank - Ministerial Staff (2) Q Bank -Section Controler (2) Video (2) ABB (1) FAQ (1) GDCE Exam (1) IRMS (Indian Railway Management Service (1) JUNIOR ENGINEER (Non -AC) GRADE - II (1) Minimum Wages Act (1) Project & Planning (1) Q BANK & Answer - C & W ( Carriage & Wagon ) (1) Q Bank - Instructor (1) Q Bank - AMM (1) Q Bank - All Department (1) Q Bank - Ballast Train Checker (1) Q Bank - CCTC (1) Q Bank - Complaints Inspector (1) Q Bank - GK (Computer) (1) Q Bank - Leave Rule (1) Q Bank - Mason (1) Q Bank - Maths (1) Q Bank - NPS (New Pension Scheme) (1) Q Bank - OS / Clerk Typist (1) Q Bank - Pass Rule (1) Q Bank - Planning Inspector (1) Q Bank - Railway (GK) (1) Q Bank - Stenographer (1) Q Bank - Track Machine (1) Q Bank - Traffic Costing Inspector (1) Question Bank - Technicians of TLAC Group. (1) Short Notes - Establishment (1) Short Notes - Operating / Traffic (1)